Responsibility of the architect in case of KfW interest and further matters

  • Erstellt am 2018-07-13 11:44:17

Ruhrgebiet23

2019-01-29 10:32:36
  • #1


Yes, of course. We also considered several 10k Euro buffers. But still, we should have been informed earlier.
 

Zaba12

2019-01-29 10:41:33
  • #2


You have a contract. Who is listed as the executing architect? He should be listed there! So insist on contract fulfillment. Hopefully, the contract contains not only the service phases but also the executing person.

If he is difficult, you stop everything and give him a written deadline of 14 days to manage it according to the contract. Otherwise, separate.
 

Ruhrgebiet23

2019-01-29 10:45:26
  • #3
On the fee proposal that we accepted, the letterhead states Mr. alter Architekt, Dipl-Ing, Architect. Also:
- "my fee proposal for the execution of the architectural services"
- "I would be pleased to carry out the work for you and kindly request a written assignment."
- Signed by Mr. alter Architekt

Is that sufficient?
 

Ruhrgebiet23

2019-01-29 10:52:15
  • #4
I am still not quite sure how I should talk to the structural contractor. I would have said that we were quite shocked by the amount of the excavation. He will probably argue that it was necessary. And I would like to bring up that the new situation should have been discussed, but then he will probably feel cornered immediately and I won’t get anywhere...
 

Zaba12

2019-01-29 11:13:54
  • #5

Difficult. It could be enough. But you can guess the answer in the conversation. You just need arguments to counter.
 

Zaba12

2019-01-29 11:19:16
  • #6
But keep in mind. He did not bill according to HOAI. If you separate, he can catch up on this upon separation and you are already in the service phase of construction supervision! Thus, the final bill upon separation could be higher than his fee offer.
 

Similar topics
19.07.2018Draw the plan yourself? Do you necessarily need an architect?11
18.02.2011Architect totally messed up - experiences?17
30.09.2012Final invoice architect13
27.10.2013Architect --> Agreements? What is that?21
16.04.2014Cost of soil survey - Does the architect pay or do we?12
16.09.2014Termination of collaboration with architect - demands excessive fee28
01.10.2014Collaboration with an architect - how does it work properly?22
25.02.2015Planning / Architect, involvement of specialist planners for the approval plan10
10.04.2015Cost estimate architect single-family house. Your assessment44
26.04.2015Semi-detached house architect or general contractor / prefabricated house or solid construction13
27.12.2015Who has built with an architect? Experiences??85
11.09.2015Building a garage on the boundary is not possible according to the architect.11
17.11.2015Is an architect really that expensive?46
05.04.2020Developer or architect - costs43
07.03.2016Various dimensions architect execution drawing12
06.12.2018The architect and the client cannot agree on a design22
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
10.11.2020The architect is wrong with the estimates. And now?29
31.03.2021Comparability of costs Architect vs. General Contractor119
04.10.2022Architect does not keep the schedule - what to do?21

Oben