Ruhrgebiet23
2019-01-28 20:42:46
- #1
I have one more idea, maybe someone can correct me: Is the structural shell builder commissioned according to VOB? Was his offer based on the tendered quantities? Settlement of the actual quantities at the offered unit price?
The tender documentation states: "1. The VOB applies in the version valid at the time of bidding."
Furthermore:
"2. The bidder is obliged to inform himself about the location and planning of the construction project. Documents can be inspected after arrangement with the client or planner. Claims due to ignorance of the location and planning are excluded."
The structural shell builder was also on site before contract signing, the architect informed us.
Also in the tender documentation:
Excavation for slab foundation
to be carried out according to profile, including
rough grading.
Take over excavation as property of the contractor and
remove it from the construction site, including rough grading,
disposal at an approved landfill or disposal site. Proof of proper
disposal must be provided. Landfill and disposal costs are to be included.
Excavation from ground surface,
excavation depth up to 0.80 m.
Soil class 4 and 5.
34 m³ unit price.............. total price..............
The structural shell builder entered 150,- under unit price and 5100,- under total price.