New wall, still with provisional power supply for the room:
(11.02.2019)
Due to the reduced room size, we rearranged the furniture, disposed of a cabinet, and installed a new countertop.
(22.03.2019)
The 735mm sliding door came much later. Again, everyone was overwhelmed, but at Hornbach they were able to place a free text order. After eight weeks of delivery time, the door arrived at the end of August and was installed.
(27.08.2019)
Now I only need a carpenter for the matching door frame (hence the gap).
Due to the reduced room size, we rearranged the furniture, disposed of a cabinet, and installed a new countertop.
The 735mm sliding door came much later. Again, everyone was overwhelmed, but at Hornbach they were able to place a free text order. After eight weeks of delivery time, the door arrived at the end of August and was installed.
Now I only need a carpenter for the matching door frame (hence the gap).