Status as of mid-February 2019:
In the sauna room and laundry room, tiles and old pipes were removed, walls sanded down and replastered, old electrical wiring removed.
In the process, interesting things from the predecessors were found. This is the busbar on the ceiling to the three-phase socket of the washing machine. Presumably, the aluminum anchor was live for years.
The damp corner and outer wall to the stairs in the laundry room have not yet been plastered until the moisture problem is resolved.
Core drillings through the concrete ceiling were carried out with an anchored (not so easy) stationary drill. The borrowed 100mm crown was clearly out of balance. My own 65mm crown ran very smoothly by contrast. The drillings in the walls (calcium silicate brick) I did by hand with the 65mm crown (normal Bosch hammer). With an attachment (extraction) on the angle grinder, the walls were worked on with the grinding discs.
Adapters clay pipe->DN90 were applied in the two corners of the downpipes in the laundry room. The old water pipe passage from hallway to laundry room was reused for the power supply.
Next up are the new wastewater pipes:

(17.02.2019)
And the first water pipes are hanging on the wall:

(19.02.2019)

(22.02.2019)
To the right the still unplastered wall area, above are the future heating pipes (the old ones are still in the way, so this is a provisional stop). Below is the temporary garden water connection, since work on the wall cannot continue yet. In the middle, hot/cold for the washbasin and cold for the washing machine.

(24.02.2019)
View into the sauna room; here too, there is initially no space for the heating pipes because the old ones are in the way.
Work continues through the fireplace room, where it initially ends.
I’m slowly needing the basis for "new" electricity. We had a simple task for the electricians: new meter cabinet with fuses, surge protection, grounding/potential equalization, relocating the meter into the new cabinet and connection to the old one while keeping the old installation. Of eight companies contacted with two pictures, only two replied :-( One decline due to lack of capacity and one on-site inspection for an offer. This company was happy about a mini-job. They can always use that if other trades on a construction site cause delays for them. As long as we stay flexible, they can handle it quickly in one day.
Suddenly the day before was here, so the wall where the new meter cabinet should go was quickly prepared. In the fireplace room, on the back of the wall from the old position.

(11.03.2019)
You can clearly see how much a bit of white paint can already make a difference.
At eight o’clock the two electricians arrived, and shortly after the new cabinet was hanging:

(12.03.2019)
After four hours, they finished the wiring. (Materials and labor: €2,800)