German solid house insolvent?

  • Erstellt am 2008-12-07 19:00:12

komiproi

2009-02-24 22:23:12
  • #1
Employee DM?


So folks, folks, I had to read twice to believe what was written there! Sorry, but I’ve only read bigger nonsense in similar comments in other forums and that either came from the management of DM or from employees of DM who are afraid of soon not being able to cheat people any longer and having to leave the heated office. The writer thinks that people in the forums cannot read, I’m surprised he didn’t get cramps while writing. He blatantly ignores the hearing before the LG Gera, the insolvency applications of the companies that are being cheated out of their money and wages, who previously worked at DOMIZIL because of this incapable management of DM, excuse me, mismanaged things – namely into their own pockets and in the end left builders and craftsmen sitting with the costs, construction ruins and debts. The craftsmen who were commissioned with construction services when the money for their payment was not even there, FRAUD and a case for the public prosecutor. The only ones who have tried to achieve agreements and results in recent months were the builders and craftsmen!! The management was on vacation and usually not reachable! Or even to be reached. WE CALL YOU BACK! The whole mess here and with DM in Austria! Builders after builders. Anyone who still talks about saving DM in view of all these criminal machinations clearly has lost sight. This is not defamation, this is the actual situation! And we still get 10,000.00 EUR from them and nothing has happened for 3 months. As for winter and normally nothing turns from November anyway! Where does he live? We even worked for these guys in November and December on weekends including Sundays at the construction sites so that the builders would still get the screed in December. Construction stop. I refer again to the other forums and the company connections of the "leading figures" and their bag carriers so that they don’t diligently cheat other builders and craftsmen again with my money and the money of the builders in two months. Watch carefully who goes where with whom and takes our money along.
 

interseption

2009-02-24 23:43:58
  • #2
Bus stop is still waiting for the bus that will no longer come... I have the impression that this is a fake, and that in real life it is someone from DM! Because no builder can be that naive...
 

naja

2009-02-25 00:15:37
  • #3


@Bushaltestelle: I believe you forgot part of the sentence in your post.

It should probably say

"exactly this comment, I mean, worsens the situation here at DM that no one can use, because then it comes out what we at DM have completely messed up"

or am I wrong?

The bad thing for DM is just that the whole matter has fortunately developed such a momentum by now that the tactic of "keeping quiet and riding it out" no longer works. The builders are not as stupid as one might hope.

Oh, by the way, the post by Kompressor is impressive with quite clear facts and objectivity, which can’t necessarily be said about your posts. If you already try to unsettle the builders on behalf of DM, then please at least do it a little more cleverly.
 

Staatsanwalt

2009-02-25 00:17:56
  • #4
@ Bus stop

Hello bus stop!

I also believe that you are from DM – but the Sicilian family business ends quickly!

If you are a builder, in my opinion you have as much brains as a sparrow knee cap!

And one more thing at this point!
Even if salespeople have resigned from DM for reasons of conscience
or have assigned their claims to debt collection agencies –
the salespeople have been and still are being cheated in the dirtiest way possible!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!

No consideration for families and livelihoods either, . . . . . .
only criminals do such things. No managing director who cares for their sales force and
continuously conducted training sessions to bind the salespeople more strongly to their company.

Just ask the training manager Mr. K.G.
and ask whether he has received his fee!!!!

With respectful greetings to all those affected!
 

willhelmheld

2009-02-25 09:25:14
  • #5
I just spoke with H. Rein..., our new site manager, we are scheduled to meet at the construction site at 10:30. He will not come because..... He himself cannot say how things will proceed. He seems to me to be an honest man and is suffering from this situation himself. Now I want to finish my construction and need for that: . the names of the craftsmen. . To get out of the contract without additional costs. Can the homeowners who are almost finished help those who are still building? How about exchanging information about the craftsmen? I was satisfied with most of the craftsmen, if we pay them ourselves at the DM-agreed prices, our construction projects would continue. Please write your opinion about this.
 

eda

2009-02-25 13:27:33
  • #6
Contract

I have also signed a contract with DM.
I don’t even know what to do now when I read this.
Why doesn’t DM Haus comment on this here??
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
16.05.2015Contract unclear: humus earth collectors10
04.07.2016Building without a contract - Concerns?39
10.09.2016Construction financing and contract with the developer24
28.05.2017Plundering the Riester contract - for less need for credit?16
16.08.2018Civil engineering works without a contract - normal, experiences?10
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
09.05.2021Price adjustment clause in the contract with the general contractor18

Oben