Electrical planning - How many sockets are enough?

  • Erstellt am 2017-08-27 22:40:59

305er

2017-09-19 22:33:32
  • #1
So according to DIN they don't work anyway, only according to VDE. Unfortunately, I can't find anywhere that it must be a conduit and not just a protective tube and that it must be possible to replace it.

NYY may be crushed?

Yesterday I sent an email with these pictures to an independent expert. He is responsible for electrical engineering and installation. Today I talked to him on the phone. He told me that this does not comply with VDE, that we should immediately initiate a construction stop and nothing should be plastered. He is apparently also responsible for fire cause investigation at the criminal investigation department and said that just recently he had a case where a house burned down after 22 years, with the cause: hook nails during installation.

Another expert also said based on the pictures that he does not like it.

The construction manager only says, as long as the electrician approves it and submits some protocols where everything was measured through and everything fits, it is also okay. And if it’s only about the hook nails, they have nothing to do with the interior plaster.

Oh yes, if that is not okay, the entire cable has to be removed, including up to the junction box, which is already behind the plaster.

How does it look with the insulation/sheathing of these NYY cables? They have this thick stiff black outer layer, then a white thin “rubber skin” and then the 3 cables. Do these cables including white or black sheathing have to go into the installation box, or is it enough if it stops before and only the 3 cables go into the box, as shown in the picture?

 

DNL

2017-09-20 00:05:28
  • #2
I am not an electrician, but as far as I know, it is standard to lay the entire cable with the sheath into the boxes. It is supposed to provide protection.
 

dragonfreak

2017-09-20 12:31:48
  • #3
I do come from the industrial sector, but yes, the coating is applied all the way into the can.
 

305er

2017-09-20 21:19:59
  • #4
Hi, today I had a meeting with the project manager of the electrician company.

He went through everything with me and mostly agreed with me.

So the sheaths belong at least up to the box, if you push them in too far, you simply don’t have any space inside anymore.
He is having everything fixed everywhere and a sheath pulled over by the two guys who did everything for me.

The cables, meaning the NYY cables (underground cables), are not pinched and were also measured.
Nevertheless, he is removing the hook nails and having a perforated tape placed over them.

He is doing nothing with the protective conduit. That would be fine because with so many corners and that length, you can’t pull any cable through anymore, so it is really only for protection and not for later replacement.

In all the walls, sometimes even under the plaster, there were still hook nails.
Although one worker told me they all come out, I pulled out at least 10 nails alone in the office and guest WC.
Some cable ducts were still full of those things!
The project manager took the two employees in hand rather politely and told them again that that must not happen! That they absolutely have to come out and only serve to fix the plaster.

I think the two guys had to work overtime today =)

So apparently everything will be fixed and I am at least a bit relieved.

The two guys who were on the construction site the whole time seem to be very young!
Good that everything is public and there is Facebook ... the "older" one seems according to FB to have only started his apprenticeship there in September 2014, so probably freshly trained.
The younger one, from what I gathered a bit, talked about something like an intern and then an apprentice. Apparently also just starting with the apprenticeship.
I wouldn’t mind if at least the foreman takes over the work afterwards!

Because if I hadn’t been so on top of things and annoyed, there would now be hundreds of hook nails in the wall under the plaster and I would have rust problems on the walls later!

Tomorrow morning I will go and look at everything again!

Actually the interior plaster was supposed to come today, but I doubt they will even start tomorrow! Like every trade so far!!!! -.-
 

truce

2017-09-20 21:55:35
  • #5


Just as a comparison, how it looks with us.. I think the Elis wanted to finish quickly with you.
 

winnetou78

2017-09-20 21:56:15
  • #6
So I can fully understand you.

But I believe normally applied acrylic nails cause no problems with [übergeputzt] at all.
 

Similar topics
01.12.2015Interior plaster gypsum or lime31
16.07.2015Cable for outdoor lamp too short11
01.01.2016Cost of house connection for Kabel Deutschland and Telekom?37
17.01.2021Installation of a satellite system38
14.01.2018Kabel Deutschland or Telekom or both14
09.06.2017Computer cables and Wi-Fi router43
12.12.2017Many colorful cables for lamp connection - How to connect the lamp?11
09.09.2019DSL socket - Did I break the internet connection?10
20.02.2020What does the electrician do during the shell construction phase?19
08.04.2021Building without antenna and SAT-CAT cable without conduit?65
01.09.2020Which conduit for LAN cable?32
18.09.2020CAT cable in the utility room - not crimped?45
19.02.2021Telekom Hybrid or Vodafone Cable - Advantages & Disadvantages for Internet36
08.05.2021Connecting LED ceiling lamp - several cables hanging from the ceiling27
28.08.2021Looking for a suitable doorbell for CAT 7 cable12
11.09.2021Which Cat cables should be installed on the facade? Problems with moisture?29
21.02.2022Electric gate, bell and opener, and only one cable33
29.10.2022Is the property fully developed? - Cable is partially missing10
20.09.20225-pin cable to 3-pin cable13
28.08.2023Electrical outdoor installation - thought of everything?13

Oben