Der Sachse
2020-02-07 14:22:03
- #1
I am now a little confused. If I follow the explanations here, the civil engineer and structural engineer (a company) is still not behind schedule on Thursday in week 10, since mathematically they still have the entire Friday to carry out the earthworks, replace the soil, construct the basement room, pour the floor slab, let the floor slab dry, as well as build the shell and the ceilings. Am I seeing this correctly?