Good planning and construction supervision "cost" nothing insofar as they pay off. Here you will find, using the search terms Hausbau-Fahrplan and Gerddieter, posts in which I explain why the decision between Holzer or Steiner should not be made before the Teigruhe, between Modul A and Leistungsphase 3; and with the search terms Eigenvergabe, Einzelvergabe, Ausschreibung and Regiestunden, those in which I address the icebergs on the high seas of backfiring "stinginess". "General contractor after tender" is often not a bad way, while "general contractor instead of tender" is almost always, and very decisively so.That is a lot of money regarding construction supervision and the like. Who exactly does something like that? Are you building solidly with individual contracts for the trades or also timber frame prefabricated construction with a general contractor? I wonder if the latter would be cheaper.