Pinkiponk
2022-06-11 13:36:47
- #1
Addendum: The promised ...
PART 2:
-------
For the items where "0.00 €" is stated, we have (so far) paid nothing, but perhaps they are relevant for your construction project.
PART 2:
-------
For the items where "0.00 €" is stated, we have (so far) paid nothing, but perhaps they are relevant for your construction project.
Plot | 147,500.00 € |
Land transfer tax | 5,162.50 € |
Notary fees | 1,335.66 € |
Broker commission | 0.00 € |
Property tax (notice) | 56.25 € |
Public drinking water supply | 778.66 € |
Confirmation of secured development | 23.80 € |
Connection permit drinking water | 23.80 € |
Telephone connection | 0.00 € |
Public sewer system | 0.00 € |
Confirmation of secured development | 54.88 € |
Decision on drainage application | 140.92 € |
Soil investigation | 941.55 € |
Surveying/site plan | 568.40 € |
Site plan for building application | 475.60 € |
Site plan 1st amendment for building permit | 145.78 € |
Site plan 2nd amendment for building permit | 145.78 € |
Rough and fine staking/height reference point | 680.68 € |
Entry of mortgage in land register | 347.00 € |
Structural analysis | 4,500.00 € |
Builder’s liability insurance | 236.57 € | |||
Construction performance insurance with extended subsequent liability (12 months) | 853.53 € | |||
House and landowner liability insurance | 48.80 € | |||
Residential building insurance including shell fire insurance | 329.66 € | |||
Builder’s guarantee/deposit insurance | 208.95 € | |||
Assignment of house number | 21.50 € | |||
Transmission of data from cadastral map | 47.60 € | |||
Certificate of statutory pre-emption right | 31.65 € | |||
Court costs for land register priority notice in xyz | 177.00 € | |||
Land register entry, cancellation of priority notice | 379.00 € | |||
Cost statement notarization of mortgage in xyz | 522.46 € | |||
Review of offer/contract house construction company xyz | 595.00 € | |||
Information from building encumbrance register | 33.68 € | |||
Kitchen | 0.00 € | |||
Garden house/tool shed | 0.00 € | |||
Outdoor facilities | Driveway, paths, terrace | 0.00 € | ||
Garden and tool house | 0.00 € | |||
Hospitality for craftsmen | 500.00 € | |||
Double burden rent and loan payments | 0.00 € | |||
Construction supervisor/building surveyor/building expert | 0.00 € | |||
Topping-out ceremony | 0.00 € | |||
Housewarming | 0.00 € | |||
Building permit/certificate | 681.00 € | |||
Structural engineer | 0.00 € | |||
Confirmation of KfW funding criteria | 0.00 € | |||
Lawn/hedges/shrubs/cuttings? | 0.00 € | |||
Mailbox | 0.00 € | |||
Container with lid | Mixed construction waste, m³, with lid | 731.00 € | ||
SCHUFA credit checks for house construction company | 60.00 € | |||
Rental of construction site toilet | Price per month | 201.06 € | ||
Leakage test wastewater | 238.00 € | |||