House construction 2016 - Which and when are the next steps to take?

  • Erstellt am 2015-07-15 10:19:44

Bauexperte

2015-07-30 13:03:55
  • #1
Since I don’t know where you want to build, I’ll answer for NRW: In the simplified approval procedure between 4 and 6 weeks, in the regular building application procedure up to 3 months. In cases of §§ 34 and 36 or also agricultural old parts, it can also take longer; but it often depends on the caseworker at the office. Rhineland greetings
 

cumpa

2015-10-29 22:37:54
  • #2

Hello Bauexperte.....Through a call to KFW today I was able to find out some things.

As far as applying for the KFW loan funding is concerned, I have had it confirmed for the second time today that it is sufficient to have a financing conversation confirmed in writing (at the bank) showing that you want to take advantage of KFW funding.
However, the application must then be submitted no later than 3 months later. During that time you can even start building.
But you must not have completed more than 50% of the construction at the time of application.
Therefore, we will only hold this financing conversation at the beginning of January in order to then enjoy the higher funding 3 months later (100,000 instead of 50,000€).
But I will have that confirmed in writing as well.
Best regards, Cumpa
 

wpic

2015-10-30 00:25:44
  • #3
The tightened version of the Energy Saving Ordinance applies from 01.01.2016: the requirements for the insulation value of the components are increased by 20%, those for primary energy consumption by 25%. It is thus practically impossible to plan a building with a monolithic wall construction (aerated concrete, perforated bricks, climate light block) without additional ETICS, which drives the costs enormously higher. The gas condensing boiler without additional regenerative energy producers, previously possible through compensatory measures in the form of a 15% improved building insulation, is thus no longer possible for the time being. The costs for building services therefore also increase.

It therefore makes sense to submit the building application or start construction this year (stamp receipt of building application or start of construction notification for approval-free construction projects). However, if you have not yet carried out any preliminary planning or have not contacted an architect so far, it will be very tight. Preliminary design/design up to building application maturity takes time, depending on the complexity of the construction project, which in turn is determined, among other things, by the site situation and the associated building and planning law requirements. Is there a development plan or does §34 Building Code apply? Does a building enquiry need to be submitted before the building application? Then 01.01.2016 is no longer realistic.

You should discuss these framework conditions in an initial contact with an architect you trust. This is usually free of charge. It does not necessarily have to be the only architect who happens to have an office at the building site. What matters is the personal relationship and stylistic compatibility.

Financing can realistically only be discussed when there is preliminary planning/a preliminary design with a subsequent cost estimate from the architect. Banks/lenders will want to handle it this way. Concluding financing without this preliminary planning is risky because you have thereby definitively set the framework for the construction project before clarifying what costs will actually be incurred. Additional financing may be more expensive or not possible, or the credit framework may be set too high: if proof of use must be provided (KfW loan), this can also become problematic.

So: think it over calmly. When building and renovating, haste and spontaneous decisions are out of the question. The matter is too complex and too expensive for that.
 

Bauexperte

2015-10-30 00:38:33
  • #4

With all due respect, but that is not true.


Ack.

Rhineland regards
 

Basti2709

2015-10-30 09:27:25
  • #5
Maybe you will also be lucky and the tightening of the [Energieeinsparverordnung] in 2016 will be suspended for a few years... I have already read several reports about it... but whether it will really happen...
 

cumpa

2015-10-30 09:31:43
  • #6
KFW 55 remains KFW 55 even in 2016
 

Similar topics
19.06.2009Evaluation of the KfW 60 House Contract: Credit Check for House12
07.10.2016Which heating is recommended for KfW 55?58
19.06.2015Build according to KFW 70 or the Energy Saving Ordinance 201442
09.07.2015Energy Saving Ordinance Proof vs. Energy Saving Ordinance Proof + KfW-70 Proof13
10.05.2016KfW funding for two-family house26
11.02.2017KfW loan in 2017 for a house under the 2016 Energy Saving Ordinance17
10.12.2017Second residential unit in the house due to KfW funding 15313
24.07.2019Energy Saving Ordinance 2016 or KFW 55 for bungalow with air-water heat pump & controlled residential ventilation, optional photovoltaic47
29.01.2021Is the 2014 Energy Saving Ordinance a KfW standard?24
18.11.2021KfW funding for KfW 40 Plus houses from now and from 01.07.202157
21.03.2021Land registry later than planned - save KfW funding18
08.05.2021New building with granny flat - general contractor restricts rental and KfW funding51
31.08.2021Kfw 40 Plus funding - Ban on feed-in tariff?21
12.11.2021Exclusion of funding / Purchase contract signed before KFW grant10
14.06.2022KfW BEG funding stopped 261, 262, 263, 264, 461, 463, 4641239
02.10.2025KfW Funding Climate-Friendly Residential Building from March 2023167
19.07.2023Double KFW 297 funding through two residential units?16
31.10.2024KFW 300 Funding - Attractiveness23
11.01.2025KfW 300 funding upon disposal of real estate ownership10
16.08.2025Single-family house with 2 residential units for KFW funding35

Oben