Maybe I misunderstood the calculation...
You have 135,000 EUR equity and wanted a 400,000 EUR loan, so a total of 535,000 EUR. The 100,000 EUR was a rough estimate; I based the calculation on that and thought you would end up at least at 635,000 EUR. So not 100,000 EUR on top of the current construction costs, but rather taking out about 100,000 EUR more loan...
There could still be additional costs for earthworks. I already mentioned the electrical work. Small expenses can also add up. And I don’t understand the proportionality between a high-end standard and 3-LAN sockets, no cables, and no satellite. But well, everyone is different.
Sanitary fixtures? You don’t have those included at all! Have you even picked any out? How much do they cost? Is the acquaintance doing it for free? Outdoor facilities? 20k-30k? Where are all the incidental construction costs? Construction power, permits, etc.