The house has actually been standing for a good 15 days now, the pace is amazing...
- Assembly day (1) 05.04
- Assembly day (2) 06.04
- Electrical installation 06.04-11.04
- Roof covering 10.04
- Drywall 06-11.04
- Underfloor heating and sanitary preparation 19-20.04
- Screed 24-25.04
- Planned handover 16.05.2017
Currently we are still in the selection phase for the garage provider and paving.
The fence was ordered this week and will be tackled one week after the house is completed.
So far I have to say that we are very happy with Danwood