Is the general contractor payment plan acceptable? Thanks for tips

  • Erstellt am 2018-08-18 00:30:45

Ybias78

2020-09-24 08:15:45
  • #1


Since a planning contract is made first, in the worst case €20,000 is "gone". Although it is not really gone, since the building permit is valid for 3 years.

But I cannot arrange financing if I do not know the total sum. The bank will hardly accept an amount x split into:
- house costs
- incidental construction costs
- exterior facilities.

I have received the addresses of the individual trades. Once I have the floor plan, I will get in touch with them.
 

K1300S

2020-09-24 08:21:42
  • #2
Phew, difficult matter. 20 K is already quite a bit in case the construction project fails due to financing. As I said: In our case, it was only 1800 EUR, and ancillary construction costs and outdoor facilities can be estimated approximately, but the house costs should actually be known before a design planning, which costs five figures. Of course, something can still change there, but hopefully not in a jeopardizing range.

Isn't there a possibility to get a house price without detailed planning?
 

Ybias78

2020-09-24 08:27:45
  • #3


We already have a house price including special requests like photovoltaic system, rainwater cistern, ceiling height 3m, etc. It is currently at €320,000 (house price only, without additional building costs). But a five-figure amount will definitely be added. Since we have sent a few changes regarding windows, entrance area including door to the general contractor. Also, the exterior walls are supposed to be decorated with some stones (women!!!). I have planned a total of €357,000. So there is still about €37,000 room to move upwards. However, I cannot submit €357,000 as financing if the offer states €320,000.
 

K1300S

2020-09-24 08:29:46
  • #4
Well, then you do have your numbers. And yes, you *CAN* provide the 357 K. You should just break down what is included in there. (Boden, Wand, Aufmusterung Fenster, ...) This will then also be accepted – with a stamp from the architect – even by ING.
 

Ybias78

2020-09-24 08:31:13
  • #5


And is that enough? Doesn't the bank need the general contractor's offer? Or a construction contract?
 

Tolentino

2020-09-24 08:37:53
  • #6
yes she needs it, but the amount does not have to correspond to the total amount of the construction costs. This is then a separate document where you additionally enter incidental construction costs and, for example, [Aufmusterungen]. This construction cost summary can also be stamped by your [GU].
 

Similar topics
05.02.2014Costs/planning land, additional construction costs, turnkey, etc.27
19.11.2014Financing single-family house - How much can we afford?47
14.11.2013Is financing for construction projects feasible?10
11.10.2022List of incidental construction costs. More expensive "on the builder's side"?154
19.08.2014Home construction financing - House price and ancillary construction costs27
21.08.2014Is financing without equity realistic?19
19.10.2015Financing - Your opinion is needed15
29.01.2016At what value is the property assessed during financing?24
31.03.2016Financing / house building feasible?24
20.01.2021Financing: How much did your house cost?166
08.08.2016Financing of construction projects45
14.12.2016House planning, offer, financing, fixed price19
17.01.2017Is financing feasible? Finished house for the money?60
31.01.2017Financing house construction is feasible47
10.04.2017Banks for 110% financing169
24.06.2017Construction ancillary costs: Bank requires signature from the architect16
19.08.2018Is construction financing possible like this? Or where is the mistake?18
21.10.2019Financing with building savings loan + KfW + subordinated loan17
13.10.2020Land available - ancillary construction costs, ancillary house costs, financing?34
14.01.2021URGENT: Plausibility Check of Additional Construction Costs - 2 Days Before Deadline43

Oben