Is the general contractor payment plan acceptable? Thanks for tips

  • Erstellt am 2018-08-18 00:30:45

Obstlerbaum

2018-08-24 15:03:05
  • #1
50% after window installation is somewhat ambitious, but not that far from what is actually possible. Our construction contract provides for an initial payment of 48% after roofing, with 5% held as a security deposit according to the Building Code. Another 17% after heating installation and sanitary/electrical wiring and window installation... Short version: I personally would never accept the mentioned offer.
 

erazorlll

2020-09-06 15:20:03
  • #2
To avoid having to start a new thread, I would like to join in here.

We have received the payment plan from our general contractor, with the following proposal. Discussion and changes are potentially possible if they remain within reasonable limits.
What do you think about it?




















































Payment step Percent Cumulative percent
1. After contract signing 2.4%
2. Concrete slab laid 8.0% 10.4%
3. Ceiling above basement concrete 15.4% 25.9%
4. Ceiling above ground floor concrete 16.0% 41.9%
5. Completion of shell construction / roof 16.0% 57.9%
6. Completion of windows / interior plaster 16.0% 73.9%
7. Completion of interior work 16.0% 90.0%
8. Completion of exterior plaster 5.0% 95.0%
9. After acceptance 5.0% 100.0%
 

erazorlll

2020-09-23 13:55:39
  • #3
Anyone have a hint or an opinion on this? I would appreciate it.
 

ypg

2020-09-23 14:36:51
  • #4
Completely overpaid before the expensive technology is installed. But that's how it is with almost everything.
 

erazorlll

2020-09-23 14:41:26
  • #5


Thank you for your response.

The general contractor was open to changes in the payment plan in the last conversation. What would be your recommendation or for which steps should one go down and where up?
 

Ybias78

2020-09-23 15:24:33
  • #6
This would be ours for comparison:

1. Interim payment of 05 % after the start of earthworks
2. Interim payment of 10 % after concreting the floor slab
3. Interim payment of 10 % after the load-bearing masonry on the ground floor
4. Interim payment of 10 % after the load-bearing masonry on the upper floor
5. Interim payment of 10 % after erecting the roof truss
6. Interim payment of 08 % after roofing
7. Interim payment of 07 % after installation of windows
8. Interim payment of 05 % after interior plaster
9. Interim payment of 10 % after rough installation H/S/E
10. Interim payment of 05 % after earth deep drilling
11. Interim payment of 05 % after drywall
12. Interim payment of 05 % after 1st and 2nd layer of exterior plaster
13. Interim payment of 05 % after installation of stairs & interior doors
14. Interim payment of 05 % after laying tiles & completion of H/S/E
 

Similar topics
22.04.2015Window, roller shutter, exterior plaster10
08.12.2015Payment plan: paid too much at the beginning?11
26.02.2016Renegotiation of payment plan, please help25
03.05.2016Please evaluate the payment plan25
01.08.2017Questions about the payment plan10
08.09.2016Window connection / reveal in double-leaf masonry24
28.11.2016Payment plan / Guarantee remaining amount Acceptance20
09.01.2017Interior and exterior plaster in winter10
09.11.2019Sound problem: Does noise come through masonry - through the exterior plaster?20
28.02.2017Are securities customary for completion and warranty?24
17.07.2017Payment plan okay - 13% after the floor slab?21
18.08.2017First invoice for earthworks and base slab due25
09.08.2017Is exterior plastering possible before interior plastering in summer?10
30.06.2018Construction contract - Uncertainty regarding payment schedule33
19.08.2018Strategically well-planned handover completion under building supervision11
30.09.2018Payment Plan for Prefabricated House - Reviews and Experiences Desired10
04.04.2023What is more expensive? Masonry or windows?21
02.02.2020Payment plan (Broker and Developer Regulation) and Developer's payment plan10
11.12.2020Payment plan and unpleasant feeling11
29.02.2024Payment plan - 5% retention not regulated11