Tolentino
2020-09-23 15:58:32
- #1
Mine:
1 Start planning 7% 7%
2 Submit building application 5% 12%
3 Submit building permit 5% 17%
4 Foundation slab finished 10% 27%
5 Load-bearing walls ground floor finished 16% 43%
6 Roof truss erected 8% 51%
7 Roof covering finished 9% 60%
8 Windows installed 10% 70%
9 Electrical and interior plaster finished 6% 76%
10 Heating and sanitary finished 6% 82%
11 Screed finished 4% 86%
12 Exterior plaster start 4% 90%
13 Final acceptance 10% 100%
Payment schedule is more customer-friendly. However, I couldn’t negotiate at all due to time pressure.
Edit: Demolition removed, that is not done by the general contractor.
1 Start planning 7% 7%
2 Submit building application 5% 12%
3 Submit building permit 5% 17%
4 Foundation slab finished 10% 27%
5 Load-bearing walls ground floor finished 16% 43%
6 Roof truss erected 8% 51%
7 Roof covering finished 9% 60%
8 Windows installed 10% 70%
9 Electrical and interior plaster finished 6% 76%
10 Heating and sanitary finished 6% 82%
11 Screed finished 4% 86%
12 Exterior plaster start 4% 90%
13 Final acceptance 10% 100%
Payment schedule is more customer-friendly. However, I couldn’t negotiate at all due to time pressure.
Edit: Demolition removed, that is not done by the general contractor.