Do you have the land registry costs included in the real estate transfer tax or the notary position?
It includes: registration of the conveyance, deletion of the conveyance, land register entry, registration of the land charge, possibly other items. Each time with IT & postal flat fees, etc. etc. Check what this will cost you altogether, but you should plan at least 1000. The city may have to waive its pre-emption right (this also costs a fee), etc. Everyone sends nice invoices in connection with the property purchase that you did not expect.
The sample reserve is too small. At least 20000€. Staircase color? Spots, a few more sockets and combustion points, extra effort for large-format tiles (even though the tiles are included!!!) etc. etc.
Money is just slipping through our fingers and we haven’t even started with the construction itself yet. :-(
When the building ground survey is available, your general contractor can tell you what the extra costs will be. Fortunately, for us, only about 3000, since frost-resistant and foundation-capable soil lies below the 30cm topsoil.
Connection trenches, etc., are still additional.
It includes: registration of the conveyance, deletion of the conveyance, land register entry, registration of the land charge, possibly other items. Each time with IT & postal flat fees, etc. etc. Check what this will cost you altogether, but you should plan at least 1000. The city may have to waive its pre-emption right (this also costs a fee), etc. Everyone sends nice invoices in connection with the property purchase that you did not expect.
The sample reserve is too small. At least 20000€. Staircase color? Spots, a few more sockets and combustion points, extra effort for large-format tiles (even though the tiles are included!!!) etc. etc.
Money is just slipping through our fingers and we haven’t even started with the construction itself yet. :-(
When the building ground survey is available, your general contractor can tell you what the extra costs will be. Fortunately, for us, only about 3000, since frost-resistant and foundation-capable soil lies below the 30cm topsoil.
Connection trenches, etc., are still additional.