For us, it was 5 months after the screed.
1 month was lost because the house connections were not there.
But even so, it was still 4 months.
The drying time is really already forever.
And then there’s electrical, plumbing, kitchen, tiles, painting, and floors.
They all have to have that time first.
For example, our kitchen was only measured after the screed had dried, and then the delivery time was added.
The kitchen would be measured for us before the screed. Only the interior plaster was important. The manufacturing time for that is one month. We procured the appliances ourselves. After the furniture is assembled, the stonemason comes and measures the countertop.
ps: The tiler was the last craftsman for us. Maybe use this trade as a reference?
For us, it will be the interior doors. After tiles come the kitchen installer, painter including vinyl laying, and then the interior doors.