Is the building plan reliable? When to terminate the rental apartment?

  • Erstellt am 2022-05-14 08:29:54

Neubau2022

2022-05-25 09:29:26
  • #1


No, no exposed beams :cool: We’re simply suspending 11 cm with drywall. And that’s where the ducts for the controlled residential ventilation will go. Besides, we still have to decide where ceiling spots and light outlets will be installed. Otherwise, the attic will be paneled so that we have plenty of storage space. It will be over 20 sqm with a height of at least 2m.
 

stepfel

2022-05-25 17:50:49
  • #2
We gave notice the day after the handover. For painting and flooring work (not included in the house price) + kitchen, we need almost 2 months anyway, the remaining month was to prepare the old apartment for handover. Now our landlord of the old apartment told us during a viewing that he will no longer rent it out but wants to use it himself and that broom-clean is sufficient for him :D
 

motorradsilke

2022-05-30 08:23:17
  • #3


Yes, we moved into an office container on the property at the start of the demolition. However, we had already lived in the house on the property for many years. We had an office container (2.5 x 6 m, which we had previously placed elsewhere on the property) set up 1 meter away from an already standing garage. In front of it was a large party tent (4x4m), where we put the old kitchen furniture, the dining table, and some small pieces of furniture. The garage served as a cellar replacement and storage room. In the container, we had our double bed, couch, TV, a large office cabinet, and a shelf for the most important clothes. Between the garage and container was a space for a shower and chemical toilet, which we roofed over. We had basically built ourselves a small residential complex. However, the shower and toilet were only exposed to outside climate, and the kitchen only a little more, which in the summer last year really took its toll in the final weeks. We wouldn’t have managed much longer than 6 months. At first, the water in the coffee machine actually froze.
We stored the remaining furniture and items in 2 other garages on the property.

But we also had a tight schedule that had to be strictly adhered to because of the living situation. It worked out as well.
The screed arrived on 18.08, then dried for a week with lots of ventilation. After a week I set up a dehumidifier because the walls were still too wet. On 31.08 the corner for the heating was tiled, on 03.09 the heating was installed. Then 4 weeks of screed drying with the heating on, mid-September the drywall builder started and finished at the end of September. On 01.10 we started painting and laying floors. We moved in on 15.10. However, there were still no interior doors (delivery difficulties), no kitchen (Ikea also did not consider fixed delivery dates binding), and only the guest WC available. The bathroom was tiled and the fixtures installed in the following week; the doors and kitchen came mid-November. But none of that was a problem, we almost always keep doors open anyway, and for a kitchen a few tables with 2 hotplates on them worked just fine, and we still had those and the fridge. Lamps were installed gradually as I found them in the boxes. But finally being able to use the toilet again in the warmth was worth its weight in gold. The rest came over the following weeks, we still are not completely finished (tile backsplashes and kitchen windowsill are still missing, some walls will be painted colorfully in the fall), but first the outdoor facilities were important to us. We were able to remove the last construction fences 2 weeks ago when the fence was finally up, and you can hardly tell there was ever a construction site here.
 

Similar topics
21.04.2015Is a floor plan with a garage feasible on the property?29
11.06.2015Single-family house with a granny flat & garage14
29.07.2015Floor plan of a single-family house with garage18
04.09.2015House price reasonable?!76
15.08.2016Property - Building window - Location of house and garage44
20.12.2023Placement of house and garage on plot12
06.04.2018Floor plan change - Load-bearing walls in the apartment. What to do?14
10.02.2020Place house, garage / carport on the property93
02.04.2019Cost estimation of house to determine the budget for the land63
07.11.2019Single-family house 172 sqm with garage and sauna54
09.12.2019Heating in the kitchen "necessary"?35
06.05.2020Feasibility single-family house + land 550k-600k NRW75
13.05.2020Single-family house 11.35x9.65 floor plan and placement on the property29
05.05.2020Correct execution of thermal separation house/garage16
28.07.2020Single-family house 160m2 with basement, 500m2 plot108
20.10.2021Alignment of house and garage on the property18
22.09.2022Alignment of house on property12
25.05.2023Plot Single-family house New development area60
29.06.2023Position of garage on property, specification in development plan22
26.03.2025Orientation of single-family house + garage on west-east plot with street on the west18

Oben