mayglow
2024-11-16 23:03:51
- #1
Another month has passed. The thread reminds me that things are definitely progressing, even if there are occasional little problems here and there.
So what have we achieved:
- after a lot of drama, water, electricity, and fiber optic cables are in the house! (Nothing happens with those inside the house - but let’s be happy about the things that are there) There were probably 14-15 back-and-forths about whether each provider digs by themselves and opens up the street or not, and if not, who works together with whom (and then three times around again), but hey, the cables are now in the house!
- after a bit of drama the painter is now also finished! (For us it was mainly delays, but in our opinion, the work was decent. For the neighbors, it was the sub-subcontractor and at times quite shoddy.)
- we have a kitchen! Without electricity and water, but a kitchen (and we also immediately intensified our construction site monitoring – phew)
- we have a foundation for the prefabricated garage. Also later than originally planned, but it was an important step for us.
Currently in progress:
- we have taken the first steps in the fine installation of electricity (and there are the next little problems)
- the landscaping gardener is still busy outside, rainwater and wastewater connections are in progress, and next week the garden is supposed to be leveled.
- we are currently laying laminate ourselves.
What should start soon:
- erect the garage!
- fine installation of sanitary and heating(?) – allegedly we were supposed to be scheduled in November, but that is already halfway through. Heating is still a question mark because of electricity, and the outdoor unit has to go on the garage.
- next week we will get a front door!
Briefly about the electricity again: We had feared it a bit, but from the start we were told "it would be good if you continue with the previous electrician" – well, only he didn’t want to. Now it is apparently sometimes tedious for the successor to find out what is where (or not). According to current assessment, the employee on site doesn’t really feel like it either, so it tends to take even longer. Sigh. But step by step it’s also moving forward.
So what have we achieved:
- after a lot of drama, water, electricity, and fiber optic cables are in the house! (Nothing happens with those inside the house - but let’s be happy about the things that are there) There were probably 14-15 back-and-forths about whether each provider digs by themselves and opens up the street or not, and if not, who works together with whom (and then three times around again), but hey, the cables are now in the house!
- after a bit of drama the painter is now also finished! (For us it was mainly delays, but in our opinion, the work was decent. For the neighbors, it was the sub-subcontractor and at times quite shoddy.)
- we have a kitchen! Without electricity and water, but a kitchen (and we also immediately intensified our construction site monitoring – phew)
- we have a foundation for the prefabricated garage. Also later than originally planned, but it was an important step for us.
Currently in progress:
- we have taken the first steps in the fine installation of electricity (and there are the next little problems)
- the landscaping gardener is still busy outside, rainwater and wastewater connections are in progress, and next week the garden is supposed to be leveled.
- we are currently laying laminate ourselves.
What should start soon:
- erect the garage!
- fine installation of sanitary and heating(?) – allegedly we were supposed to be scheduled in November, but that is already halfway through. Heating is still a question mark because of electricity, and the outdoor unit has to go on the garage.
- next week we will get a front door!
Briefly about the electricity again: We had feared it a bit, but from the start we were told "it would be good if you continue with the previous electrician" – well, only he didn’t want to. Now it is apparently sometimes tedious for the successor to find out what is where (or not). According to current assessment, the employee on site doesn’t really feel like it either, so it tends to take even longer. Sigh. But step by step it’s also moving forward.