Reference current construction prices / Build now or wait?

  • Erstellt am 2023-10-21 07:55:58

kati1337

2023-12-23 09:01:44
  • #1
We have given everything to a single general contractor who is then responsible for the entire project. This is partly because you only have one point of contact if something comes up. If there is a problem or deficiency somewhere, trades tend to say "it's not their fault," based on our experience with the first build. And then I don't care who tries to shift the blame. Because our general contractor is responsible, and he has to take care of getting it fixed, which fortunately he does in our case.
 

Allthewayup

2023-12-23 09:09:44
  • #2
Despite having a civil engineering degree in the family (stepfather), we did not go for individual contracting because at the time we started it was impossible to find companies for the individual trades. That was only possible through the network of a general contractor (GU) who fully utilized the capacities of the companies. Today, almost 1.5 years later, I am rather back to individual contracting. In your case, however, everything may have gone well (so far). If construction defects occur, you must first clarify the question of fault. Depending on the damage, this can become a big problem. With the GU there is "one face to the customer." This also applies to later warranty matters. And although we have 5 or 6 architects among friends and acquaintances, they all said back then that we should rather start with a GU at the moment. Two of the architects have even built with a GU themselves but took over the supervision themselves. One of them even has an ongoing case with his GU due to massive defects in his special windows. What I want to say is that there is no standard path and it also requires some luck.
 

heaaat_

2023-12-23 09:36:14
  • #3


I totally agree with you. If you do the contracting yourself, you have to be fully committed and, of course, you are not immune to defects. So far we have had 2-3 issues and all were resolved very accommodatingly (e.g. the passage to the slightly lower floor was only 2 meters high due to the upper floor slab – the plan specified 2.50m – although I had signed off the wrong floor slab with the builder before ordering, he chipped out about 0.4m x 1.0m from the slab including reinforcement without complaining). Getting companies at the beginning of the year was also difficult – we started early but had the feeling that the craftsmen made some space for us to be able to carry out our order. Unfortunately, the windows came about 2 months later – that caught us out a bit. As an "apology," we got the exterior window sills at purchase price.
 

11ant

2023-12-23 15:17:29
  • #4

The characteristic of otherwise usually sharp negotiators and skilled purchasers is – and it’s incredibly hard for me to believe this is just coincidence – a significantly frequent trait of owners who pay at least financially for DIY contracting lessons, as well as (I almost want to say “comorbid”) ...

... so the scope of the architect’s planning ends with performance phase 4 – not even phase 5 at least! – and the subsequent awarding without the helmet and harness of performance phases 6 and 7 :-(

So the architect only sits out phases 5 to 7 and then participates again in phase 8?


This is delicate insofar as it can lead to parameters that are unfortunately not taken into account during planning (you don’t have to make it such a textbook example of a deterrent as with his “let’s-see-what’s-happening stair hole”). And the “countless consultation talks” are probably only a very slight exaggeration that you first need to be able to afford (time is money or something, plus you also need a lot of time to possibly read up on know-how first).

You almost behaved commendably regarding the number of offers. It is significantly important that the providers can realize they are not being held in a “counteroffer marathon.” Equally important is also ...

... that they do not get the impression the client wants to hold court on the backs of the craftsmen, who then have to starve on dry bread. You apparently are the client type of :-)

That might be quite nice to show excerpt-wise for illustration, e.g. – please link here – in the house pictures thread 14011.

Just an upper floor with one floor slab certainly also strains my imagination quite strongly without pictures ;-)

Not only the house, but you apparently are also not exactly the type “role model for everyone to copy.”


That, in turn, is – with the small fine exception of the lucky find, unfortunately as with Mr. Rossi – a prototypical example of the motivation to go the GC route. And GCs aren’t per se “wrong,” only the widespread custom to commission them without tendering.


That’s the second, just as classic plea along the same lines (I have grayed out one sentence with a question mark).


That’s how it is: a GC must always be viewed as a contractor who naturally can never check itself from the client’s side with impartiality.

This was already shown here (four, five?) years ago by : that GCs rather own the “08/15” domain, require stricter control for “08/15 de Luxe / 7016,” and pose an increased risk for “4711.”
 

heaaat_

2023-12-23 15:47:40
  • #5
In the end, the architect later prepared the proofs for the loan on an hourly basis, showing which trades had already been completed. In this context, he praised the high quality of the trades.
: So what is ultimately your recommendation for building the house? Architect, general contractor, or self-management? Financially, we are overall about 10% above the original offers. However, we had anticipated that. I compare myself to the neighbors, and in terms of cost, we are definitely much better off (it is a new development with about 40 new single-family houses).
We have spoken with various architects; I am not convinced that an architect is an expert in all trades. The experts for the respective trades are the craftsmen themselves. Of course, the architect knows from experience what to pay attention to, and building without an architect is a bigger risk than with one. But every new build is different here as well.
 

Radfahrer

2023-12-23 18:07:13
  • #6
General contracting is almost unknown to us.
He profits from every trade.
Craftsmen have a reputation.
Good, expensive, affordable, cheap, won’t come, etc.
You can already make a preliminary selection of whom to request a quote from.
Although we are from a different industry, we performed a relatively high amount of work ourselves
which was a godsend for the general contractor to avoid a complaint.
 

Similar topics
15.07.2014Foundation slab for Danwood bungalow? Company for complete works?11
11.02.2015Cost planning for a single-family house including land, additional costs, architect32
11.11.2014The Old Suffering - Turnkey/Individual Contract38
06.10.2016Base plate with defects?22
22.07.2017Horizontal sealing of the base slab24
18.08.2017First invoice for earthworks and base slab due25
27.10.2017Construction description by architects: Who has experience?13
14.03.2018Slight slope, building with a basement or a floor slab?16
11.07.2019Possibility of preliminary questions to architects23
26.04.2020Are phases 1-4 sufficient? Or additionally 5?11
01.07.2020Complete offer from the architect? Is the price reasonable?54
06.01.2022Architects or prefab house cost calculation and next steps27
15.11.2021Wishlist for the architect32
27.12.2021Base plate pedestal height measurement17
22.05.2022Are performance phases 1-3 with the architect and lump sum offer somehow disadvantageous?19
18.01.2023Architect performance phase 1-4 - Which documents are required?33
25.06.2022Is the cost estimation by the architect realistic?39
12.02.2024Preliminary design via the architect and then tendering?16
13.11.2023Catalog house or free planning with architects12
03.03.2024Basement or ground slab: which is more sensible for the property situation?55

Oben