Yes, true, just thought about it recently. So first of all, I read again what was on the invoice, it explicitly states advance payment of x% of the amount x. Since we haven’t agreed on any partial acceptance anywhere, I really assume that it is as you say. That the acceptance then basically takes place at the end of the house, and that this is also what is meant in the contract.
Yes, regarding the floor slab and everything underneath, it can’t be checked anymore now. According to the construction supervisor, that’s a shame because it is important, since after all the house stands on it. But unfortunately, nothing can be changed now. The first appointment is scheduled for next week. He wants to look at the shell and the roof up to the supporting battens. I am quite excited.
About a construction status report: No, we don’t have anything like that. I hadn’t heard of it before either. We were told that of course we will receive extensive documentation. But I think that will happen in the end. And there will surely be something about the structure or the execution of the floor slab.
But you’re right, I need to calm down... You just hear, read and see so incredibly much that goes wrong. And with such a large amount... I don’t want any damage that might possibly harm my wife and little child (e.g. mold) or something like that.
Ah, sometimes it’s hard.