Additional construction costs when building a house with a developer

  • Erstellt am 2022-03-12 00:02:45

SoL

2022-03-12 16:17:57
  • #1
Have you at least had the [Bauleistungsbeschreibung] professionally reviewed? Probably not, judging by how the thread has been going so far...

No offense, but you really have no idea and have signed a contract, probably without knowing what is missing from it / disadvantageous for you.

If necessary, have it reviewed retrospectively now, so at least you know what to expect...

Otherwise, very likely a very abrupt and nasty awakening will come during the course of the construction...
 

Bertram100

2022-03-12 16:21:37
  • #2

That would give me pause. :confused:
 

Lupfer1

2022-03-12 16:29:41
  • #3
The surveying by the surveying office you have to pay for yourself.

Ok thanks. How much is that approximately? Around 1000 euros?

Overall a crazy price. Either got lucky or there will be more to come.

Until now, I wasn't really aware that this is very good price-wise. Maybe it's because my sister went to school with him and since I told him from the start that I want to build with him, he might have left out one or two percent markup in the end. Or there really will be one or two more things coming, which I hope not. With the costs I have just learned about here, it might just work out if the loan cannot be changed anymore.
 

Lupfer1

2022-03-12 17:00:50
  • #4


No, unfortunately we did not have the construction service specification reviewed. I had people from my circle of acquaintances read it who have either built themselves or understand something about construction. No one really knew if the prices were good or bad, because for most it was just too long ago and you can’t compare the prices with those from 5 or 10 years ago. But no one noticed anything negative about the description itself. I am aware that I currently have no idea about building. I just think that won’t change unless you take decisive action. I was lucky to still be approved for KfW55 and lucky to get a still fairly favorable interest rate. If I call it off now or postpone it, that would probably mean it becomes more expensive again, and then the loan amount might again not be sufficient. The builder said he has me scheduled for July, provided the building permit doesn’t take too long, so that the roof is closed by winter and the windows are installed.
 

SoL

2022-03-12 17:10:27
  • #5
Then I’ll stick to my eyes closed and push through. But please mentally prepare yourselves for massive additional costs. Should they not occur after all and all the other builders in this forum simply pay too much and you have found the only nice BU in the republic, then rejoice in hindsight.
 

11ant

2022-03-12 17:12:56
  • #6

475+56 would be 531k, so the big question is: what happens with the financing if it becomes +15% (= 611k)?
I hope the stove is purely for coziness, does not play a relevant role in the heating calculation, and could also be reserved for retrofitting. It would be best if you show the design in a new thread linked here (so that the completed questionnaire can be included in the opening post), because otherwise our ideas about the complexity are very much guesswork; and you should also add the construction service description. With the current vague information, one can basically only wish you good luck but give few substantial hints.
 

Similar topics
18.07.2012What should be considered in a construction service description?10
19.03.2014Comparison of construction performance description! What should we prefer?47
01.12.2016Construction company rejects change requests in construction service description and construction contract39
13.03.2017Construction planning, construction work description, cost breakdown19
01.12.2017The bank may want a construction service description despite individual subcontract awarding26
31.03.2018Prices have been lumped after modification ideas of the construction service description10
01.08.2018Description of construction services - Performance assessment?12
29.10.2018Earthworks in the construction performance description17
12.04.2019Is the construction performance description detailed enough?14
14.11.2019Have you understood your construction service description?49
23.01.2020Construction work description - Thin slab foundation disadvantageous?11
17.04.2020Construction Performance Description Formulation13
11.06.2021Construction performance description from the favorite - Is something missing?65
24.04.2022Comparison of construction work description regarding the base slab17
10.08.2022Foundation cushioning Town & Country house construction service description10
16.08.2022Evaluation of Offer + Construction Description of New Bungalow29
18.06.2023Assessment of offer, description of construction services12
18.03.2025Overview of the offer and construction work description20