House construction: Prefabricated house or solid house? Experiences Price range

  • Erstellt am 2022-06-10 16:50:04

ollininjo

2022-06-10 16:50:04
  • #1
Good day everyone,

we have been dealing with the topic of building a house for several months now. Unfortunately, we are quite "new" in this field and do not know all the details about everything. Of course, we have read a lot and googled, but you often read very different things and especially older and not very current ones.

We have a plot of land in view, here in the city. It amounts to 830 m2 including partial development. The cost of the plot is 130,000 euros, and of course, you have to add the real estate transfer tax, notary, and land registry fees (anything forgotten?). Since the plot is only partially developed, all the connections are, according to the provider, in front of the street, because the plot was parceled out. Then, of course, you would still pay development costs; we are estimating about 10,000 euros.
In total, we would then be at about 150,000 euros for the plot, so far so good.

Now comes the house; we tend more towards a prefab house, since a custom architect-designed house does require a lot of work, doesn't it? Of course, I have already looked through several providers, and there are always some nice prices. We are now assuming a 150 m2 prefab house, where a price of 380,000 euros is indicated to me, including all the services the provider offers. Provided I do it turnkey, what costs would one still have to expect? I think garage/outdoor facilities are clear; are there other costs that need to be factored in? Maybe someone here has experience with such a build and could help us.
We would just like a rough estimate of whether many more costs would be added, because then one would be at over 600,000 euros for a 150 m2 prefab house, which is a bit unclear to me.

Thanks in advance to everyone!
 

SoL

2022-06-10 18:18:07
  • #2
Welcome to the forum. Please read through the thousands of budget threads, you will find what you are looking for there. You still have site surveys, earthworks, connection costs, construction supervision, construction power, building permits, ... to come. Feel free to check the service description of the provider for "bauseits" and "seitens des Bauherren" or "bauherrenseitig". These are also things you have to take care of. As I said, read up first, you will learn a lot...
 

Neubau2022

2022-06-10 18:36:48
  • #3
That is quite helpful when you fill out the questionnaire. Because if, for example, you start without equity and with a household income of €4,000, there is no need to give tips, as it will not be sufficient.

Your standard would also be interesting. What do you want:
- Bungalow or city villa?
- Air-water heat pump or ground-water heat pump with deep drilling?
- Controlled residential ventilation?
- Air conditioning?
- Fireplace?
- Smart home or even KNX?
- and, and, and...

The area where you are building is also important. Prices vary significantly from state to state.

After that, you can certainly make good estimates of the prices you have to calculate with and how high the interest rates could be...
 

HoisleBauer22

2022-06-11 09:16:20
  • #4
In the thread there is already a lot on the topic. Conclusion in one sentence: A comparison is very difficult because pears are not apples and there are many (regional) varieties of pears and apples. About the costs, which somehow automatically increase ;-) :
 

HoisleBauer22

2022-06-11 11:03:40
  • #5
Regarding ancillary construction costs (as of the end of 2021 in the Southwest:)
 

Pinkiponk

2022-06-11 12:54:31
  • #6
Also a warm welcome from me to the forum. :)

Here is the first part of our additional costs for the house, the second part will follow shortly after processing. The amounts marked "confirmed" are already binding through offer and order confirmation, the other figures are estimated, extrapolated, based on experience and/or researched.

PART 1:
-------
--> We built "turnkey," but awarded additional contracts for, among other things, MSH, tiles, painting, plumbing, electrical work. If you have questions about individual details, feel free to get in touch. :) I copied an Excel table here and hope everything is somewhat understandable and/or readable.

Period: March 2022 until now
Object: Prefabricated timber frame house, two full floors, no basement, no convertible attic, hipped roof
Heating/hot water supply: Gas condensing boiler with solar thermal system (underfloor heating)
Size: 9.40m x 9.40m (shell dimensions)
Living space: approx. 139 sqm (shell dimensions)
Construction site: Saxony/Leipzig district

I am attaching photos to this thread, even though they are already available elsewhere in this forum.

[ATTACH alt="IMG-20220325-WA0002.jpg" type="full"]72559[/ATTACH][ATTACH alt="IMG-20220325-WA0000.jpg" type="full"]72560[/ATTACH]











































































































































































































































Company xyz Plumbing (6-sided bathtub, 2x shower trays, etc.) confirmed
5,287
Plumbing own work (2x shower cabin, 2x washbasin, 2x WC, 2x fittings)
1,950
Electrical surcharge (plus €600 paid on 03.06.22)
2,380

400
Kitchen cabinets 0% financing
1,400
Painting additional costs
6,000
Tiles additional costs confirmed
2,501
Surveying/cadastre registration
500
Gas connection confirmed
649
Media connection Company xyz confirmed
999
Construction power/construction water according to consumption (construction power approx. €410)
700
Tips
1,200

300
Extension of waste container 4 months week/€19.90
320
Cleaning layer/spray protection strip around the house
1,500
Move to xyz
1,400
Garage foundation
1,500
Garage
11,000
Drywall additional costs
530
Electricity connection
500
Drinking water connection
779
Acceptance wastewater connection
177
Construction water connection
444
Construction power connection
200
Electricity order for provision of temporary connection
100
House connection column electricity connection and rental
195
Insurances
1,200
Construction site toilet 1 month
201
Waste container 7 cbm with lid
713
Additional orders floor slab, MSH
4,298
Leak test wastewater
238
Earthworks, preparation of crane location
20,000
Crane location, road closure
1,712.98
Statics Company xyz
4,500
 

Similar topics
02.09.2013Angular bungalow on 800m² plot - financially feasible?16
27.05.2013Cost estimation: prefabricated house, basement, carport, single garage10
25.06.2014Financial requirements for building a prefabricated house55
14.07.2015Turnkey home. Free land17
02.03.2015Turnkey house construction, but with own room layout?17
31.03.2015Property / Financing amount / Insurance? Experiences10
16.11.2016Broadband supply for the new development area over my property17
01.02.2021Single-family house 159 sqm - Straight plot - Correctly calculated?26
19.10.2020Street about 50cm above the property - backfill or basement24
12.05.2022Is the budget for a prefab house (turnkey) realistic?15
06.01.2023Solid house or prefabricated house? Semi-detached house, approx. 160 sqm, pros and cons22
29.06.2023Position of garage on property, specification in development plan22
31.07.2023Connection of wallbox in the garage23
26.03.2025Orientation of single-family house + garage on west-east plot with street on the west18
07.02.2025Cost issue for earthworks on a slope22