Wow, is that really the case? Because yesterday I saw an offer from other acquaintances. They are building something quite comparable but have a flat rate that's only half as high as our offer! That's quite tempting...
 

Zaba12

2018-03-14 12:19:50
  • #2
If it ends badly already. Same story as without a contract, demand payment according to [HOAI]. It also always depends on your counterpart and your behavior in the existing business relationship.
 

junge_familie

2018-03-14 13:30:30
  • #3


What I still can't figure out:

    [*]If the 325,000 euros are the eligible costs and
    [*]If they are correctly stated as net and
    [*]If we assume that the total costs are 50% above the eligible costs,

then our small semi-detached house with its good 100 sqm costs well over 500,000 euros. That is all absurd...
 

Alex85

2018-03-14 13:40:38
  • #4
Yes, you need to have explained to you where this amount comes from and how/whether the fee adjustment will be agreed upon if this amount is not reached.

In addition, you can ask acquaintances who have used the inexpensive architect whether they also commissioned service phases 1-8 or if any services were excluded.

You can also ask the potential partner how often he will be on the construction site. I have received answers ranging from "when an appointment is scheduled" to "daily." The latter certainly involves more effort. Site supervision and documentation (service phase 8) account for 32% of the fee... if you just sit in the living room, that's rather easy money, possibly at the expense of quality.
 

arnonyme

2018-03-14 14:05:45
  • #5
I think we paid almost 50k in fees for service phases 1-8 back then when we were with an architect, according to his specifications. However, the total costs were about 550k. So somehow that seems relatively expensive to me.
 

toxicmolotof

2018-03-14 14:19:59
  • #6
Just a side note from me, because much has already been said and we also built with an architect.

We started with a budget of 200k (house + incidental building costs), after visits to several architects we ended up at 250k. In the end, it was 330k. And the garden is not even close to finished.

And I think the argument "self-inflicted" to dismiss "no time" is wrong. I want and have to take that idea away from you, even at the risk of becoming unpopular.

It is your damn duty to deal with it. Either yourself by investing time or by money. If in doubt, more money than you like. A "I didn't know because I had no time" does not interest any judge. Cf. ignorance of the law excuses no one.
 

Similar topics
18.02.2011Architect totally messed up - experiences?17
10.04.2015Cost estimate architect single-family house. Your assessment44
11.09.2015Building a garage on the boundary is not possible according to the architect.11
20.02.2017Finance construction project, total costs: €395,00052
10.11.2017House plan by architect 2 floors with basement18
09.12.2017Renovation with architect: Suggestions for house floor plan desired21
10.10.2019Single-family house by architect 150m² improvement suggestions and ideas wanted75
31.03.2020Massive house provider or architect in Corona times19
26.04.2020Are phases 1-4 sufficient? Or additionally 5?11
03.09.2020Modern single-family house with architect in southern Germany25
10.11.2020The architect is wrong with the estimates. And now?29
07.02.2021Single-family house, two floor plan variants from the architect39
18.02.2022Floor plan offer from the architect - your opinion11
18.01.2023Architect performance phase 1-4 - Which documents are required?33
27.05.2022Architect - Flat-rate offer instead of HOAI for single-family house12
11.03.2024Is the architect's cost estimate realistic?10
30.08.2024Renovation or demolition and new construction - decision support from the architect?25
14.09.2024New construction cost calculation, suitable for architect?30

Oben