Alessandro
2020-09-09 13:42:08
- #1
The progress invoices already include items such as "completion of the shell construction work," "completion of the screed work," and so on. However, the contract states for the final invoice, which is still outstanding, "final payment after acceptance and final invoice" in the amount of 5%. There will therefore be a final acceptance of all contractual services from the foundation slab to the exterior plaster. On the internet, you often read that if a lump sum price including VAT was agreed upon, the VAT reduction may not be applied retroactively to progress invoices already paid. However, mine explicitly states "lump sum price xxx incl. 19% VAT."