Subwkloofer
2020-06-09 08:44:50
- #1
Correct, that’s how it is. Sometimes contracts include special clauses that hedge a “more probable” VAT increase for the contractor but also credit an “unlikely” VAT reduction for the client. The decisive factor is the acceptance and the associated start of the warranty period and the full performance of the general contractor. So folks, make sure to get your acceptance done this year.Exactly. The partial payments according to the installment/payment plan only have the character of advance payments on the agreed total price. Therefore, it is relatively simple: Date of final acceptance = Date of performance. Ergo, you should make sure to get the final acceptance done by 31.12.2020. Example: - Completion and final acceptance on July 15, 2020 - Total construction costs: 450 TEUR gross (incl. 19% VAT) according to the construction contract; of which 400 TEUR already paid in installments Final invoice: 450 TEUR / 1.19 * 1.16 = 438.7 TEUR Payable with final invoice: 38.7 TEUR Savings or indirect subsidy: 11.3 TEUR