Are securities customary for completion and warranty?

  • Erstellt am 2017-02-23 13:57:39

Bieber0815

2017-02-23 15:50:23
  • #1
We withheld 5% of the total amount from the first installment. This retention was due "simultaneously" with acceptance (finished, but not free of defects). If there are major defects, it is not finished, then you can (should) refuse acceptance and of course not pay. In case of less serious defects, you are obliged to accept and pay. However, you can claim a retention (usually double the cost of defect rectification), which you deduct from the installment due upon acceptance.
 

DragonyxXL

2017-02-24 11:24:29
  • #2
Due to current events:

We negotiated our payment plan back then.

1st installment 15% after completion of the foundation slab
2nd installment 15% after completion of the ground floor (it is anyway just a bungalow)
3rd installment 15% after completion of the roofing

The construction company is now insolvent and we have paid about 40% for the almost finished shell with all its defects.

We still have a completion guarantee of 5%, which we will most likely have to use completely.

At Town & Country I saw a payment plan with 60% upon completion of the shell. Then we would have a huge problem now.

Would our construction company have accepted 30-35% up to shell completion? Definitely not!

Paying according to construction progress is nice and good, but if the payment plan is unfavorable or undetailed, it doesn’t help either.

Just a few examples:

Does the chimney count as part of the ground floor?

What about the ceiling/roof insulation if no installment payment is defined for drywall?

In which installment payment is the formwork of the roof overhang included?
 

stefanc84

2017-02-24 14:04:31
  • #3
It would be 50% at the moment up to and including roofing. Even more problematic, I find the final payment of only 1%. That means if they don’t finish it and don’t fix defects, they only have to forfeit the last percent, in this case just €2,100. That means we would be in a pretty bad position then?
 

Bieber0815

2017-02-24 14:19:53
  • #4
What does the last percent of completion include? You shouldn't pay for defects (keyword retention).
 

stefanc84

2017-02-24 14:55:34
  • #5
Remaining work from the acceptance protocol.
 

Bieber0815

2017-02-24 17:28:09
  • #6
Well then, all good! You only pay the 99% for acceptance if really only minor issues remain. If there are many or serious defects (or open works), then you withhold accordingly more money (double the defect rectification costs) or refuse acceptance.
 

Similar topics
26.02.2016Renegotiation of payment plan, please help25
28.11.2016Payment plan / Guarantee remaining amount Acceptance20
11.03.2018Optimization of Angle Bungalow 108 by Town & Country21
08.10.2020Is the general contractor payment plan acceptable? Thanks for tips68
29.02.2024Payment plan - 5% retention not regulated11

Oben