Mh, we already had six-figure offers for garage, floor slab, retaining wall (at the same time house wall and garage wall), earthworks for house connections
Here are a few floor plans
Just take a look around.
Otherwise readytorumble did a lot of work himself. He knows what costs come up, also all the "additional costs" from the trowel over joint adhesive up to the concrete mixer.
Also consider how much time you can and want to actually spend on the construction site week by week, month by month. Many friends and acquaintances also do not want to spend their free time on the construction site in the coming months.
Don’t plan too tight. If things don’t work out with the Poles, you’ll have a problem. Better to have money left over and thereby execute the 1st special repayment than to need refinancing or spend years without a terrace and garden for the kids to play.
Here are a few floor plans
Just take a look around.
Otherwise readytorumble did a lot of work himself. He knows what costs come up, also all the "additional costs" from the trowel over joint adhesive up to the concrete mixer.
Also consider how much time you can and want to actually spend on the construction site week by week, month by month. Many friends and acquaintances also do not want to spend their free time on the construction site in the coming months.
Don’t plan too tight. If things don’t work out with the Poles, you’ll have a problem. Better to have money left over and thereby execute the 1st special repayment than to need refinancing or spend years without a terrace and garden for the kids to play.