Bram05
2018-10-22 10:49:50
- #1
I might get harshly attacked for this post, but I still want to briefly add my two cents.
We signed in June 2017, started construction in October, and moved in July 2018. We built about 40 km east of Dortmund. According to the contract, our house cost 216,000 euros, and a 6x3m prefabricated garage was included.
Our salary situation was very similar to yours, but we didn’t even have a third of your equity. If I had requested the project here back then, I probably would have been massively scared and intimidated. Whether the construction would have ever happened – rather doubtful.
I just want to say that these inquiries here are useful, but often the worst-case scenario is highlighted. As I said, useful, but sometimes a bit unsettling.
For example, our garage was calculated at 6,000 euros, and that already included a power outlet, as well as an internal and external light point. Foundation included too. When I read here that a garage costs 15,000 euros and then you have to calculate a few thousand more for the electrics, I wonder what kind of luxurious garage that should be.
Our plot was quite cheap at 50,000 euros, so in the end we only borrowed 310,000 euros, and even had a few thousand left over. I’m well aware that we may not be the rule, but it doesn’t always look as bleak as one might get the impression here. (We also had some problems, you can read them here, but these cost us almost only nerves and time.)
I don’t want to attack anyone posting here, just shed some light where there is a lot of shadow.
Regards
P.S.: Of course, I want to join the previous posters regarding the plot. Finding the right land is at least as difficult for us as finding someone who will build a house on it. So first find the suitable land.
Thank you very much for your post and the quite extensive feedback... Such answers are welcome and extremely constructive. I know it doesn’t always have to or can go that way, and many stumbling blocks have to be overcome to reach such a state.
In my opinion, you already made the first cliché mistake by choosing a floor plan (according to your statement your optimum) without having the matching plot for it.
You’ve now also heard that it can go cheaply. It just requires decisiveness – namely to reject all options that cost more money than originally planned/available. Of course, that also works, but for that one (!) should determine and weigh everything beforehand and not only during the construction process.
Since you can read various things here and basically don’t want to know anything about possibly missing items, I'm out.
Oh Maria... What else can I say?!
I get hit over the head with the price frame because it’s supposedly calculated totally unrealistically… So far so good, then my question about where the alleged costs are is more than understandable, right?!
Where does it say that I don’t want or assume no hints… Sorry but that is just nonsense again and unfortunately misinterpreted.
My reference to the original background of the thread was aimed at the friendly user who “has to shove all info up my backside”…
And thus hasn’t quite understood the causal chain either.
And finally, about our so-called cliché mistake – yes, we don’t yet have a plot and yes, we don’t yet know which house may be built on a possible plot. But we have various options for exactly such a scenario. Regarding the floor plans, we currently only took one variant of a standard floor plan and expanded it with minor things like a shower in the guest WC, or the bedroom with a walk-in closet, no more and no less.
I believe this is not planned too far ahead yet.
Accordingly, I would be very happy if you could explain the possible mistake to me and maybe show a better solution.
If you are actually out of the topic now, thanks anyway for your contribution.
Best regards, Bram