Building without work plans

  • Erstellt am 2016-06-23 08:47:09

Bauexperte

2016-07-29 14:05:30
  • #1
Good day Mr. Tunsch,


As I have written elsewhere, *I* would not *want* to conduct a comparable dispute in a public forum. The mutual positions are clearly entrenched, emotions and counterstatements alternate; no consensus is in sight.

The moderated forum is intended to enable a first step towards rapprochement; to lay the groundwork for objectivity and thereby subsequently enable personal conversations. To give a criticized provider the opportunity to describe their view of the situation. Under no circumstances should the moderated forum be used exclusively as an exchange platform for mutual accusations. If you and are unable to communicate on a factual and reasonable level, I again recommend putting the matter in the hands of a lawyer.


As long as you continue to argue factually, I will approve every post; the same applies to . As a moderator, I only decide which wording is published insofar as the content must be composed according to the forum rules and be factual. How much you want to disclose about the business relationship with your customer is therefore entirely up to you.

Rhenish greetings
 

alter0029

2016-07-29 14:10:17
  • #2
You should have made a reasonable offer for exiting the contract, then everyone would have been helped. #Assumption deleted; construction expert. Crediting €1450 for the approval planning, but then wanting to keep €16,500 yourself, then €10,000, and finally €6,500 is as unprofessional as everything I have experienced with you.

In this regard, I quote from the email dated 5.2.2016 that I received from the Norddeutsche Planungsgesellschaft:
Dear Mr. G.,
regarding an appointment with Mr. K. on the construction site, I would like to offer you Friday, February 12, 2016, at 1 p.m..
Please confirm this appointment.
Furthermore, I would like to inform you that you have given us the approval for the building application, and with the handover of your building application to you, we have initiated all necessary steps for your building request.
No further appointments after the planning discussion are scheduled, which is why we have to charge for this additional effort.
In your favor, we are charging you for the garage planning as an additional service instead of the planning service based on hourly billing.

This is what your architectural services look like!
The garage, which was planned from the beginning in our plan and whose foundation is part of the construction contract, is being put forward to have an argument, #Assumption deleted; construction expert.
 

NSK GmbH

2016-07-29 14:21:43
  • #3


I cannot for the life of me see at what point we are supposed to have anything to do with your garage. You ordered it directly from a garage provider. The correspondence also clearly proves that you very well knew that garage planning was not part of our planning task:

On December 16, 2015 at 2:23 PM you wrote to the architectural office
"Dear Ms. K.,
where the two parking spaces are drawn in the building application, a double garage is to be built. It will be a prefabricated concrete garage. In Baden-Württemberg, a building permit is required for this. What costs would I have to expect if I asked you (or npg) for the building application? The structural analysis and construction description will be provided by the garage company."


On December 16, 2015, you were offered a quote of 450 € for the application of a prefabricated garage.
 

NSK GmbH

2016-07-29 14:27:06
  • #4
Thank you very much for your statement. We are very reluctant to take the dispute public, but we would like to comment on the allegations. Actually, there is no reason for this, as the matter is already in the hands of lawyers. However, as long as our client continues to raise new issues here, we have to respond to them (are allowed to). Of course, this is not enjoyable for us. We would gladly like to put an end to it in order to be able to devote ourselves to our actual work.
 

NSK GmbH

2016-07-29 14:45:30
  • #5


This statement is not quite correct. You yourself know that our last offer was made at Mr. H.'s initiative. You did not agree to cancel the contract because, I quote, "I would get into trouble myself, as it will probably be difficult to find a company soon that can step in." I may point out that Mr. H. even named a construction company for you that would have built you a closed shell.



I consider it dishonest to cite an email taken out of context. Why should you have made an inquiry about the building application if the garage planning had been agreed upon?
 

NSK GmbH

2016-07-29 14:48:08
  • #6
You will be able to tell us who the man was that you visited together with the architect to discuss the building application. Or do you want to make us believe now that this "meeting" did not take place?
 

Similar topics
02.01.2012Semi-detached house - who submits the building application first, wins?29
29.10.2013Property reserved, construction financing plan, architect/building permit application21
17.12.2014Building application "deferred". What does that mean?19
28.02.2015Building application submitted/open detailed questions/looking forward to suggestions39
15.06.2015Garage - Building Application - Confusion36
30.10.2015Can the building application be submitted this year?14
01.02.2017Building application is becoming increasingly complicated!20
27.04.2017Carport deviation from the building application21
07.06.2017Permeable traffic areas in the building application17
04.08.2017Building application or building notification15
06.12.2017Constantly making the same mistakes in the building application - stupidity or intent?44
20.11.2020Wait with the building application because of the child construction allowance1354
11.05.2018Construction application costs only 40 euros due to exemption application?27
08.08.2018Neighbor objects after approved building application69
14.10.2018Building application - delay due to neighbor's lawsuit - experiences?21
17.12.2018What is set in stone in the building permit application?10
04.01.2019Terrain modeling different from the building application - allowed? (NRW)36
26.02.2019Submit a building application before the land is paid for?11
15.06.2020Period between submitting the building application and moving into the new house11
05.08.2020Building a garden shed... Is a building permit necessary? Detours?17