Antjeaergert
2025-02-11 14:48:18
- #1
There is a cost estimate - in which the possible construction costs are listed - each given with a maximum and a minimum value.
An application for monument funding was also submitted, which must also include the estimated costs.
I thought this estimate, the calculation, and the determination according to DIN 276 were basic services according to the HOAI.
The costs for the masons alone were exceeded by 90,000 euros - which, given the targeted total costs of 400,000, already represents a considerable overrun.
The client was my father, who is widowed and wanted to fulfill a small dream. He simply resigned within the 4 years - bore the costs, repeatedly pointed out that the targeted construction costs could no longer be met.
At some point he just wanted to finish the construction - during the construction period he lived in a vacation apartment at the age of 72.
Now the architect would like the remaining 80,000 euros that she calculated in total - and from this point on I basically got involved. Because I believe she must at least provide the cost determination - where the overrun becomes clear.
She denies everything and just said she does not have to provide this.
An application for monument funding was also submitted, which must also include the estimated costs.
I thought this estimate, the calculation, and the determination according to DIN 276 were basic services according to the HOAI.
The costs for the masons alone were exceeded by 90,000 euros - which, given the targeted total costs of 400,000, already represents a considerable overrun.
The client was my father, who is widowed and wanted to fulfill a small dream. He simply resigned within the 4 years - bore the costs, repeatedly pointed out that the targeted construction costs could no longer be met.
At some point he just wanted to finish the construction - during the construction period he lived in a vacation apartment at the age of 72.
Now the architect would like the remaining 80,000 euros that she calculated in total - and from this point on I basically got involved. Because I believe she must at least provide the cost determination - where the overrun becomes clear.
She denies everything and just said she does not have to provide this.