Is an offer binding or are deviations allowed?

  • Erstellt am 2018-07-05 20:03:57

HilfeHilfe

2018-08-12 19:18:26
  • #1
I find single awarding difficult. Who requested all the technical details? The construction supervisor or you? I would never trust myself to do that!
 

Snowy36

2018-08-12 19:23:29
  • #2
Which details in particular do you mean, for example?

As explained, the construction supervisor is responsible for that...

The rest was common sense regarding the planning itself.....

And I am sure: with the general contractor, we wouldn’t have even questioned what is on the roof.....
 

Payday

2018-08-13 14:15:00
  • #3
The great thing about the general contractor (GU) is that there is EXACTLY one contact person. No matter what the subcontractors mess up, the contact person is the GU. With individual contracts, two parties shift the blame and you can settle it in court. With the GU, that is not possible because he is always contractually the contact person. Now that's just how it is for the time being. And again: what does your expert say? That he initially does not count in court is irrelevant right now. The point is to find a solution now. He knows it, he knows which section the matter belongs to or where the error lies. Otherwise, that is simply the risk of architect-led construction compared to construction by a GU.
 

Grantlhaua

2018-08-13 14:36:52
  • #4


and this is how the general contractor excuses himself, who has much more "power" than an individual trade. I don't know what is better.
 

MayrCh

2018-08-13 15:35:16
  • #5
Exactly, now we are going around in circles. What was the basis for the offer/order/assignment of the carpenter? A work or execution plan? A specification? Was this deviated from and did you approve the deviation? If the ordered target from the order letter/work plan/specification deviates from the performance provided, there is a defect. This defect is reported, with an appropriate deadline for rectification. Did you even accept the roof?
 

Payday

2018-08-13 20:48:58
  • #6


he can't make excuses like "not my problem" because he is responsible for all aspects of the ordered work.
we had one case after moving in. one roller shutter didn't work, which couldn't be seen during handover because the electric shutters were only put into operation afterwards. contacted the window manufacturer "roller shutter not functioning." window manufacturer sent the producer, who then said there was no power to the roller shutter. contacted electrician, who then said there was power at the handover junction box.
logically, the cable from the junction box to the roller shutter was broken (first the stupid question: why doesn't the roller shutter manufacturer just replace it? he should have seen/measured it...)
contacted window manufacturer that he should do something – answer: I'm not responsible for the electrics
contacted electrician – I'm only responsible up to the junction box
well, no one wanted to commission the system

so: contacted the general contractor with window manufacturer and electrician in CC: roller shutter not functioning, cable defective between junction box and roller shutter. both subs refuse to fix the defect. please do something...
2 weeks later the window manufacturer showed up and replaced the cable (carpenter).
the whole story took so long that I first installed a pleated blind on the window...
 

Similar topics
10.04.2014Are roller shutters (where) dispensable?26
16.07.2015Cable for outdoor lamp too short11
21.10.2015Which roller shutter motors are suitable for central control?18
15.05.2017Upgrade roller shutter control later and central vs decentralized14
20.02.2020What does the electrician do during the shell construction phase?19
04.02.2020Installation of additional insulation for underfloor heating - cables lie on the raw floor slab25
07.09.2021Wi-Fi New Construction - Network Sockets/Cables53
01.09.2020Which conduit for LAN cable?32
18.09.2020CAT cable in the utility room - not crimped?45
19.05.2023Smart home roller shutters / venetian blinds with conventional electricity79
21.07.2021Problem with the electrician - what would you do?78
29.01.2021Should the awning maker make corrections here? - Is this a defect?11
08.05.2021Connecting LED ceiling lamp - several cables hanging from the ceiling27
04.11.2021Control roller shutters via app New construction14
04.01.2022How to distribute and connect SAT cable and Ethernet?16
28.11.2022Do you need LAN cables in the garage?107
20.09.20225-pin cable to 3-pin cable13
09.07.2023Electrician Cost Estimate - New Installation22
24.06.2024Roller shutters let through a lot of light33

Oben