Update. In December, the windows finally arrived before work continued in January. The electrical rough-in, plumbing rough-in, and interior plastering were installed. We were also able to continue work on the double garage, which is owner-performed work. The ceiling was poured there this week. A 6000l retention cistern was installed. The house connections were also put in. Fiber optic is still missing. The floor construction inside the house may begin next week before the underfloor heating can be installed. Attached are a few pictures from December '22 until now.