Evaluation cellar / settlement house Bavaria

  • Erstellt am 2019-07-21 12:08:11

Peter Silie

2020-03-19 13:51:47
  • #1
We are making good progress.

- The plumber has installed a hot water pipe in the guest WC and installed all the flush tanks and connections in the house according to our wishes. Supply and waste pipes completely renewed, radiators are already on site and pre-installed.

- Electrician is currently working inside and will finish the complete rough installation next week.

- Windows are coming next Tuesday.

- Afterwards, the balcony will be done.

- Bathrooms in April.

- Walls closed, floors in, kitchen and finished.

So far no downtime, everything is running. I am curious about the windows, because of [Corona], delays may occur here.

So far everything is good, let’s hope it continues like this.

Regards
 

Climbee

2020-04-01 08:42:05
  • #2
I would be curious to see photos...
 

Peter Silie

2020-04-01 08:44:00
  • #3

 

Peter Silie

2020-04-01 08:50:42
  • #4

[ATTACH alt="EBEC86F6-68A9-48C9-8A49-2385BB0FD430.jpeg" type="full"]44765[/ATTACH]
 

Peter Silie

2020-04-01 08:52:09
  • #5
 

Peter Silie

2020-07-20 10:52:51
  • #6
Update 20.07:

- Electrical work finished, the sub-distribution in the basement was done last week, the rest will be done when the plasterers are finished outside
- Windows are installed, there were a few minor issues here and there, but they were fixed without any problems by the window installation company
- Water supply pipes in the house have been 80% replaced, the ones we kept were from the late 90s and looked good
- Wastewater pipes have been 98% replaced. We kept two small sections in the guest WC because they were in good condition, the rest was replaced
- Heating pipes were kept because they were in good condition
- Sloped ceilings in the rooms insulated, but not doubled, the top floor ceiling will be insulated soon
- Both bathrooms – guest WC and upstairs bathroom – newly tiled and fitted with new connections
- Doors adapted to standard dimensions
- Balcony resealed and equipped with a natural stone carpet
- Radiators newly ordered

- Interior doors have been ordered, a bit of country house style, the kitchen was also tiled and ordered, it should arrive at the end of August, parquet was bought already in March, it will be installed after the plasterers

The plasterers have been working inside since today. Except for the KZ and the office, all walls will be plastered and the ceilings covered with woodchip wallpaper. KZ and office will be completely wallpapered. The office might become a second KZ at some point, giving you more design options then.
 

Similar topics
08.10.2015Advice and tips on house plans (single-family house 1.5 stories)53
09.03.2018Radiator or underfloor heating: What is recommended under these circumstances?23
18.12.2018How do you assess this house? How much budget will be necessary?135
04.12.2018Toilet window in the guest WC next to the entrance door - is it now a no-go?44
28.06.2019Guest WC: Lower the ceiling or cover the pipe?16
08.07.2019Bungalow 135 sqm: Floor plan + windows104
27.01.2020Light connection wrong place guest WC29
14.02.2020Example cold water tap for guest WC12
19.02.2020Location of guest WC - entrance area?28
08.06.2020Single-family house for 4 people - Opinions250
24.04.2020Guest WC (1.65 sqm) and bathroom (4.88 sqm) renovation21
28.04.2020REH - Floor plan planning - Kitchen too small30
16.05.2020Guest WC arrangement - tips?19
08.06.2020City villa with office - Feedback & smart optimization ideas requested45
29.04.2021Is it possible to have a window in the guest WC/guest room despite the garage?33
02.07.2021Roller shutters in the guest bathroom, yes or no?35
01.06.2022Ground floor layout ideas for a semi-detached house49
31.05.2022Do radiators always have to be placed under the windows in new buildings?41
12.10.2022Planning guest bathroom, need your tips17
15.12.2022Planning guest WC in new construction - How big should it be? (DIN?)107

Oben