Duration until the issuance of the building permit in BW

  • Erstellt am 2020-12-15 13:08:06

11ant

2021-02-02 00:17:00
  • #1
Isn't that then practically already a permit due to the expiry of the deadline?
 

Martial.white

2021-02-02 07:04:08
  • #2


With our friends, the building authority then asked a question shortly before the deadline expired, so the deadline did not run out.
 

erazorlll

2021-02-02 16:48:37
  • #3


I didn't read the entire state building code, only the relevant parts. But the deadlines don't specify what happens when the deadline expires.
So a deadline is set, but without sanction or consequence. The funny thing is that if the municipality or a participating authority (e.g. environmental office, etc.) doesn't respond within 1 month, it is considered approval. But this does not apply to the final release by the building authority. In the end, what I lack is the written building approval or the red dot – without that I can't start.



According to the state building code, however, the deadline is only "paused" for the duration of the inquiry. So if, for example, I receive a query on 01/15 and submit it properly on 01/20, then, according to my understanding, the deadline may only be extended by 5 days.

But I can tell you, we had really serious issues regarding deadlines etc.
As I said, I’m happy to report on it, but only once I have the approval in hand. You never know...
 

Evelyn!

2021-03-13 16:24:03
  • #4
Füchsle how are you building? Stone by stone, prefabricated? Do you already have companies that are an option? I am looking! I got the building permit after 3 redesigns and 2 years!!! Deadlines or not, I was told you could file a lawsuit but by the time it goes through I probably would have the permit anyway and I wouldn’t be surprised if the building application then just goes back down the pile :rolleyes:
 

erazorlll

2021-03-14 22:37:41
  • #5


Look further up, 11ant linked my thread about looking for a house building company in the Stuttgart area. We had Köhler, Hauser, and U-Haus in the final selection, all brick by brick.

Respect for 2 years for the building permit, I'm already annoyed about the 5 months. Why or what made you redesign 3 times? And in which district was that?
 

Evelyn!

2021-03-15 09:41:16
  • #6
Hello, yes I found the thread with the house providers. Very good overview! Thanks for that! :cool: Yes, the two years were spent planning, the architect took three quarters of a year until he submitted it even though it was basically already clear what I wanted, and then unfortunately he planned significantly too large because he should have counted the balcony and terrace towards the floor area ratio but he thought that wasn’t the case and that you are always allowed to plan a bit larger anyway. But it was actually about 5m² and according to him, a cover sheet change would have sufficed if it hadn’t been approved.. In the end, there was an exceedance of 33% and since he already got his money after submitting, I think he wasn’t very keen on re-planning anymore and that dragged on again. His statement about the misplanning was that my plot was to blame, it was simply too small and with all the chaos of things to consider, no one could have kept track :mad: I have to say, there is a development plan and the architect didn’t submit the first planning to this building authority.. The second time they then failed to maintain the setback areas to the neighbors so it had to be changed again and after 2 1/4 years I finally had my building permit! Simply fantastic. The architect then wanted an additional payment for the re-planning, which I did not pay since it was obviously his own fault and of course I also had to pay extra for the withdrawn building application at the authority.
 

Similar topics
15.02.2011Building permit application12
15.06.2015Garage - Building Application - Confusion36
28.11.2024Neighbor's lawsuit against approved building permit46
20.06.2016Building Authority Approval10
11.04.2017Building authority wants site inspection116
31.12.2017Winter garden conversion - building permit required or permit-free?15
08.01.2018According to the law, the building permit is automatically granted if12
22.01.2018Building on still foreign land - Waiting for building permit25
21.06.2018What must be included in the building permit? Legal certainty?19
26.01.2019Building permit from 1931 not adhered to35
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
02.09.2019Problems with neighbor's encroachment and building authority11
19.10.2019Building permit before construction financing?11
25.11.2019Exemption procedure or building permit40
02.04.2020Architect costs? What did you pay? What price is normal?35
23.09.2020Child construction allowance with non-final building permit49
17.11.2021Official liability building permit neighbor - keywords sought14
04.10.2022Architect does not keep the schedule - what to do?21
25.04.2023Access to Rear Plot: Legal Situation for Building Permit18
28.06.2024Building permit - is a lawyer useful?12

Oben