Bieber0815
2017-10-19 06:45:39
- #1
Exactly, you have to prove damage first and then you can demand compensation. If the other party rejects the claim (which is to be expected), you have to sue. Good luck! To avoid this, you can agree on: 100 euros per working day beyond the completion date ... something like that. A specialist lawyer for construction law provides useful text modules. This may be less than the actual damage in individual cases, but it is an immediate claim that does not have to be litigated first.Proven and reasonable compensation for damages.
There it states 5% of the remaining amount if 30% for the land (after the start of earthworks) have been paid first. And 5 * 70 / 100 = 3.5. Whether the general contractor (from whom you are not buying land anyway) should therefore agree to 5% is doubtful.In the Real Estate Agent and Property Developer Ordinance, I even find final rates of 5%.
Then that’s how it is and it would be okay for me, as long as the overall price of the general contractor is okay (including the 4000 euros). Sounds silly, but I would still hire my own consultant, independent of the general contractor.They absolutely did not want to remove it.
Well, you want to optimize the whole package and presumably you won't find a general contractor where everything (!) fits, even the price.Or better to focus on the points of completion date, payment schedule and withholding as well as the exclusion of the expert?
Which aspects are particularly important to you, we cannot say. For me, build quality is above all. Then punctuality. The payment schedule should be assessed taking into account the general contractor’s solvency. Is he close to bankruptcy or does he appear solid according to the figures? Annual financial statements can be found in the Federal Gazette. Often the financing bank, if available, can also give advice.
And then: You never know in advance who you are dealing with. There are supposed to be general contractors who keep the completion date they gave by handshake. And then there are contracting parties where you only have what was once signed in black and white. How your counterpart ticks, you may only find out afterwards. Annoying in housebuilding, which is usually done only once and in which you invest “everything”. A dilemma.