Bauherrin123
2025-08-26 12:23:37
- #1
Okay, true, that is an argument that they are not necessarily responsible for it. They only approve or control it, and architects should act consultatively in advance. We simply had bad luck with the architect. I also said from the beginning that she was not motivated either. So, two parties came together who just prolonged the start – with constant ping-pong, in which both, sometimes rightly, sometimes wrongly, blamed each other. We were the ones who suffered. That is why I was fine with settling it directly with the office, preparing the documents myself, and having the architect only put the stamp on it so that the building permit went through.
Since we no longer have an architect and I have only had bad experiences so far, I have trained myself, submitted the preliminary building application, and will personally hand it in on Thursday. A terrace and a roof are also something different from house construction – that can be done afterward without an architect.
The office was also an obstacle in everything. Maybe that is why it was good to get the most important things (house, bay window, parking spaces) approved first and start with them. Otherwise, we might have already failed at the terrace roof, and everything else would have been further delayed.
Certainly, it would have been less work for me if everything had been included in one application. But just as the office did not want to move or make any effort, the same was true for the architect. I was dependent on both and made the best of it. Even if I had thought about it back then, I wouldn't have added anything – I just wanted the house to be finished.
Since the same employees are still at the office, I will now see how they decide. However, I don't think they would decide very differently today than they did back then.
It is also often the case that architects plan something and the office then objects. Then replanning is necessary, especially when much is a matter of interpretation and at the discretion of the caseworker. And if they have a certain scope, they should at least act honestly and consultatively, as someone wrote above. But that was not the case for me.
I must also say that much that architects rely on – for example, that grass grid stones or eco-paving are only counted half or proportionally towards the floor area ratio – was fully counted here at the office. The office had a few special peculiarities, and ultimately you just had to negotiate. I won with the bay window, but only because the owner of the property works in the building office in another federal state, was knowledgeable, and helped me. The architect had no clue and was brushed off.
That is why I find my way okay: I applied for my two large terraces with my desired roof, then I find out what is possible and what is not, can negotiate, make compromises, and think again about the covering and stones for the terrace or the roof.
I have a gardener, the price is right, I decided the size of the terrace, the preliminary building application is running, and in parallel, I am still choosing what I would like... Sometimes things just have to run in parallel and start together; in the end, you can decide individually how to proceed.
I am curious.
Since we no longer have an architect and I have only had bad experiences so far, I have trained myself, submitted the preliminary building application, and will personally hand it in on Thursday. A terrace and a roof are also something different from house construction – that can be done afterward without an architect.
The office was also an obstacle in everything. Maybe that is why it was good to get the most important things (house, bay window, parking spaces) approved first and start with them. Otherwise, we might have already failed at the terrace roof, and everything else would have been further delayed.
Certainly, it would have been less work for me if everything had been included in one application. But just as the office did not want to move or make any effort, the same was true for the architect. I was dependent on both and made the best of it. Even if I had thought about it back then, I wouldn't have added anything – I just wanted the house to be finished.
Since the same employees are still at the office, I will now see how they decide. However, I don't think they would decide very differently today than they did back then.
It is also often the case that architects plan something and the office then objects. Then replanning is necessary, especially when much is a matter of interpretation and at the discretion of the caseworker. And if they have a certain scope, they should at least act honestly and consultatively, as someone wrote above. But that was not the case for me.
I must also say that much that architects rely on – for example, that grass grid stones or eco-paving are only counted half or proportionally towards the floor area ratio – was fully counted here at the office. The office had a few special peculiarities, and ultimately you just had to negotiate. I won with the bay window, but only because the owner of the property works in the building office in another federal state, was knowledgeable, and helped me. The architect had no clue and was brushed off.
That is why I find my way okay: I applied for my two large terraces with my desired roof, then I find out what is possible and what is not, can negotiate, make compromises, and think again about the covering and stones for the terrace or the roof.
I have a gardener, the price is right, I decided the size of the terrace, the preliminary building application is running, and in parallel, I am still choosing what I would like... Sometimes things just have to run in parallel and start together; in the end, you can decide individually how to proceed.
I am curious.