Payment terms for prefab house

  • Erstellt am 2017-06-10 07:32:22

ONeill

2017-06-11 08:09:02
  • #1
We also built a prefabricated house and after the screed we still had the following work to do: filling Q3, installation of heating and ventilation, final electrical installation, final sanitary installation, exterior plaster, floor coverings, painting. You cannot set a 5% discount for that.

Therefore, you cannot generally say that 5% is okay for a prefabricated house. Even in the other case, 5% after the screed is clearly too little, and if your builder is not willing to negotiate, I would really consider whether a change might be better.

There could of course be mitigating circumstances if you have several positive personal preferences and you know that the company is financially sound.
 

frank_gayer

2017-06-11 08:31:38
  • #2
Unfortunately, it is not negotiable with the house builder. However, it is Okal Haus, so I am less worried about my money here
 

KingSong

2017-06-11 12:25:02
  • #3
Really Okal House? Good luck with your project...
 

frank_gayer

2017-06-11 12:28:23
  • #4
What speaks against it? That sounds negative!
 

KingSong

2017-06-11 13:32:05
  • #5
Basically, there is probably nothing against it, we also wanted to build with Okal Haus, but it turned out that Okal Haus, even after repeated inquiries, is not able (or does not want) to tell us, for example, the specific wall construction. Neither in the construction specification nor upon request do you get told which materials and thicknesses are used. The excuse was always that one cannot commit to materials because of constantly changing regulations, which is of course nonsense. We presented the construction specification from Okal Haus to an expert, and he pointed out so many gaps and loopholes that we declined gratefully. Not to mention the outrageous price that Okal Haus offered.
 

frank_gayer

2017-06-11 14:27:29
  • #6
It is explicitly stated in the construction service description, but I don't know when you built.
 

Similar topics
29.09.2009Prefabricated house, comparison to noise pollution in solid construction11
18.07.2012What should be considered in a construction service description?10
26.12.2012Prefabricated house / solid house, which construction companies?16
19.03.2014Comparison of construction performance description! What should we prefer?47
08.05.2014Most moisture from screed?25
01.12.2016Construction company rejects change requests in construction service description and construction contract39
13.03.2017Construction planning, construction work description, cost breakdown19
01.12.2017The bank may want a construction service description despite individual subcontract awarding26
27.06.2018Prefabricated house provider with electrical installation as own work14
18.04.2025Construction company wanted in the Stuttgart metropolitan area!212
21.12.2019Prefabricated house or solid house16
31.05.2020Prefabricated house construction - Ingolstadt area42
26.02.2022Concrete floor without screed on the upper floor/attic, what to do?24
27.05.2024Construction of an approximately 190 sqm city villa in Hessen (Wetteraukreis)71
12.09.2022Damp wall due to lack of ventilation after screed39
20.02.2023House purchase single-family house built in 77 how to assess?75
30.07.2024Solid house or prefab house - experiences?39

Oben