Tom1978
2021-09-09 08:36:19
- #1
And also from personal experience and the current cost boom. Signing a construction contract before you have the building permit or are about to get it is very risky. The building permit, including conversion, currently takes at least 8-9 months in Potsdam-Mittelmark. Before that, a lot is also discussed/planned with the general contractor, so you quickly lose the fixed-price commitment. And if you have also taken out construction financing, you quickly pay commitment interest, since the 12 months run out quickly there as well. I can currently advise everyone to first agree on a planning contract with the general contractor or to commission an architect who will at least work until the building permit is obtained. Only then sign the construction contract.