First alleged fixed price and now additional costs - legal?

  • Erstellt am 2021-07-07 16:49:58

Zaba12

2021-07-09 09:17:46
  • #1

Either I misunderstand something or you do.
You wrote: If the general contractor does not conduct an inspection, then he cannot request additional payment.
I wrote: This was already addressed 2 pages earlier, namely if the GC states in the standard GC contract that the fixed price applies under the lump sum for structural engineering (steel) and foundation (earthworks). If the lump sum is exceeded, then additional claims apply.
The conditions on site exactly influence this point from the contract. If the lump sum assumption (removing 30cm topsoil and soil quality is good) applies, then the lump sum holds and the fixed price is maintained; if there are deviations from the assumption and the lump sum, then there is an additional claim.

Is it stated like this in the construction contract? Hence also the statement that the GC has no risk at all with such standard fixed price offers with lump sums. And what counts is not the vendor’s talk but solely the contract signed by the OP.
That is just crap but also nothing new.
The salesperson did inspect, but he is not the site manager and in the worst case not even an employee of the GC but self-employed.
 

haydee

2021-07-09 09:22:35
  • #2


But he can. The construction service description usually specifies exactly what is included. For example, removing 30 cm of topsoil and storing it to the side. There are also phrases included that make additional work and additional costs due to local conditions billable.
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
13.09.2012Feeling pressured into a contract, is that normal?17
29.09.2011Is construction pre-planning without signature / contract legally valid?12
22.09.2012Who else fell for a contract with a reservation clause? - Search13
16.05.2015Contract unclear: humus earth collectors10
23.08.2015Construction financing with a fixed-term contract13
04.07.2016Building without a contract - Concerns?39
10.09.2016Construction financing and contract with the developer24
28.09.2016Question about early repayment and clause in the contract41
28.05.2017Plundering the Riester contract - for less need for credit?16
16.08.2018Civil engineering works without a contract - normal, experiences?10
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
06.06.2019Completion date in General Contractor Agreement - Wording assistance62
05.08.2020Contract for land purchase - obligation to build within 2.5 years18
11.11.2020Cancellation of a contract with a plumbing company24
26.04.2021Turnkey fixed price during Corona or cost increase?43
09.05.2021Price adjustment clause in the contract with the general contractor18
05.03.2023Building in existing structures - Subsequent additional costs despite a fixed price57

Oben