Deficiencies in the new construction. Dispute over the amount of withholdings.

  • Erstellt am 2023-03-22 13:50:58

HessamA

2023-03-22 14:56:50
  • #1
The 500€ are intended as a compensatory payment, as the developer indicates that carrying out this work would be disproportionate.
 

HessamA

2023-03-22 14:58:07
  • #2
There has been no expert report so far. Only the assessment of a friend who is a sanitary and supply technician. The expert report is to be created because we do not agree on the amount of compensation.
 

HessamA

2023-03-22 15:07:12
  • #3

Copper is more corrosion-resistant and has lower pressure losses due to pipe friction than steel pipes. However, steel pipes are more susceptible to corrosion. For example, they are not suitable for areas that are at risk of moisture.
 

Costruttrice

2023-03-22 15:18:46
  • #4


It's not that simple. You could (and should) have insisted during installation that copper pipes be installed according to the contract. Afterwards, it depends. If the installed material is unusable for the intended purpose, it will likely have to be replaced. However, if the material is common for that purpose (just cheaper), you cannot necessarily demand a replacement; it depends on proportionality and the scope of the work. If you cannot assess or quantify this yourself, I would suggest involving an expert who can financially evaluate the defects. Based on that, you can then talk with the general contractor.
 

HessamA

2023-03-22 15:25:29
  • #5
No acceptance of the individual trades was offered, so I could not check the pipes installed during construction. According to his own statement, the developer has accepted all trades from his general contractor. He should have had the duty to point out the error to his general contractor, shouldn’t he?
 

Costruttrice

2023-03-22 15:38:52
  • #6
Yes, of course he should have. That is why he is also obliged to carry out defect rectification or reduction. I just meant that as a client you don't necessarily have to trust blindly and usually also check yourself if everything is correct, unless you also bring in a construction supervisor during the construction. It is of course a different matter if you were not allowed to enter the construction site, I have no idea how it is with developers.
 

Similar topics
26.09.2011Finding tiles from other manufacturers / sample selection for builders13
09.07.2012Developer offer for single-family house - Are the construction costs acceptable?16
03.08.2012Contract Supplement to the Construction Contract by the Developer36
30.09.2012Developer - Is withdrawal from the purchase contract possible?11
23.06.2014Developer charges heavily for replanning - justified?12
27.02.2015Construction project with a developer without an official building plan, is a down payment required?12
01.03.2015The developer does not build according to the plan14
15.04.2015Duplex construction: Joint or separate developer?20
13.06.2015New construction with developer / construction drawing documents23
16.03.2016Single-family house - developer rejected25
12.05.2016Individual bathroom planning despite the developer (and saving money...)14
17.05.2016House Building Prices: Architect vs. Developer10
10.09.2016Construction financing and contract with the developer24
02.12.2016Plots in Cologne only through developers?54
01.11.2016Property developers in NRW. Can anyone recommend good property developers?10
17.10.2017Additional bathroom through the builder or just laying pipes?10
05.09.2017Developer or general contractor! Safety?30
17.10.2017Property developer or independent architect26
30.12.2017Take over the insurance from the developer after handover of keys?15
13.08.2018Pull cord of the blind torn. Is there a warranty against the developer?16

Oben