eric2610
2015-02-11 04:17:02
- #1
The plans according to which the house is currently being built apparently date from April 2014. We signed the purchase contract with the notary in November 2014. In this contract, the patio door as well as the smaller window in the basement were included. This plan was also presented to us in this form by the seller at that time. As for the window changes, these modification requests were communicated to the seller by us on January 9th, and he forwarded them to the architectural firm. It took an eternity there until they became active, and after several inquiries on my part, the plans were then completed and, according to the architects’ statement, forwarded to the seller after my approval.