Deficiencies in the new construction. Dispute over the amount of withholdings.

  • Erstellt am 2023-03-22 13:50:58

SoL

2023-03-22 15:40:04
  • #1
Nope. He has a contract with the general contractor and one with you. He accepted the trade from the general contractor. If he then has a problem with you (because you do not accept the result, because it differs from what was contractually agreed), then the problem lies with the developer. Why do you even talk to the general contractor, do you have any contractual relationship with him?
 

HessamA

2023-03-22 15:44:54
  • #2

Where did I write that we are talking to the main contractor? I only wanted to present the constellation. We only speak to the developer about the defects because we also have a contract with him. What agreements have been made between the developer and the main contractor are irrelevant to me. I agreed with the developer on copper pipes for the risers in the purchase contract or the construction description.
 

HessamA

2023-03-22 15:47:10
  • #3

At first, we simply visited the construction site spontaneously during and mostly after working hours without an appointment, and at some point were asked in writing not to enter the construction site without an appointment anymore...
 

Costruttrice

2023-03-22 16:08:26
  • #4
Yes, that is of course a limitation. But be that as it may, it is too late now anyway and you have to find a solution with the builder. To properly quantify the defects, I would have everything inspected and assessed by an expert; anything else is groping in the dark. My trust would be gone and therefore I would not blindly accept the sums offered by the builder.
 

WilderSueden

2023-03-22 16:09:02
  • #5
Are we talking about heating or potable water here? In houses from the 70s and 80s, there are often problems with copper corrosion in water pipes. Does the steel pipe last that much shorter? If you have to replace pipes, for example, after 30 years instead of 50, that is a significant defect. Then I wouldn't be satisfied with just €500.
 

HessamA

2023-03-22 16:15:35
  • #6

It concerns the riser pipes of the heating system.
 

Similar topics
16.06.2011Conclude a construction contract under reservation?10
01.12.2014Real estate transfer tax / what is the tax applied to? Which developer MUST?30
01.03.2015The developer does not build according to the plan14
15.04.2015Duplex construction: Joint or separate developer?20
13.06.2015New construction with developer / construction drawing documents23
15.03.2016Developer changes plot size25
10.09.2016Construction financing and contract with the developer24
21.07.2017Buying a terraced house from a developer - contract content?71
30.12.2017Take over the insurance from the developer after handover of keys?15
21.02.2018Original building permit documents to the construction company?28
29.05.2018Buying a house from a developer - required documents33
30.08.2019Is it sensible to have a building surveyor for condominiums from the developer?11
11.10.2018Waste on the construction site - What is tolerable?138
30.08.2019Must developers indicate immense embankment height/costs?12
04.03.2019Client-side while building with a property developer16
06.01.2020House purchase, prefabricated house from the developer with land10
09.02.2020Developer | Special Request | Cost Assumption38
13.07.2020Developer does not want to offset lump-sum damages with installments19
03.10.2025Floor plan changes for end-terrace house from the developer134
25.12.2023Behavior in case of imminent delay by the property developer48

Oben