Cost savings for demolition and new construction?

  • Erstellt am 2024-02-14 13:00:47

RayB

2024-02-14 17:41:30
  • #1
I am currently working on a similar project and can share the following "experience" regarding the tendering process, although not yet regarding the implementation.

- Check to what extent the two existing halves share a common fire wall. If this is the case, during the demolition of your half this wall must remain, i.e. your new building will move further to the side along this wall
- With separate demolition, depending on the depth of the possible new basement, underpinning of the remaining building may be necessary. Here, budget around 1-1.5k€ per meter
- Make a soil survey including contamination screening. The landfills want this information, as do the demolition companies.
- To save costs, try to strip out as much as possible, but if there is an existing gas heating system, stay away from it
- Remember that a demolition permit is mandatory. This can take up to 3 months (in our case)
- A street closure may possibly be necessary. This may have to be applied for by you. Not all demolition companies offer this
- Clarify whether the municipal ordinance for unexploded ordnance removal needs to be called in. In the neighboring municipality this is necessary... an additional 2k€
- Obtain many quotes. These can differ significantly in price!
- Possibly carry out any clearing yourself (can save costs)

These are the things I can think of off the top of my head... there is certainly more to consider.

Regardless, I consider your cost calculation very ambitious. For a similar building size but with basement and garage we have quotes in the range of 800-900k€ (solid construction - architect-designed house; presumably with a general contractor). In addition, there are the known ancillary costs, architect, structural engineer, various surveys etc. which alone have already amounted to about 70k€. However, I am fortunate to be building on my own land, so I do not have to buy the plot first.

Building a house is exciting for me, but requires a lot of preparation and I learn new knowledge every day.
 

haydee

2024-02-14 20:08:26
  • #2
We had to lay everything new from the street. The house connections were original. Find the budget too tight for your project.

We did not do the gutting ourselves. The demolition company did it. They were so fast. Besides, I would have gutted much more.
 

11ant

2024-02-14 21:13:32
  • #3
What did they leave standing that you would have ripped out as well?
 

haydee

2024-02-14 21:56:41
  • #4
I would have to look for the pictures exactly. It's been a few years. They knew exactly what was okay and what wasn't. Sometimes I was surprised how picky they were, for example insulation around the chimney, and then on the floor only what could be removed quickly and everything that took more work stayed. They didn't touch the wallpaper at all. I would have just removed everything very thoroughly. Whether wallpaper, floor, or cables
 

11ant

2024-02-14 23:18:31
  • #5
If I remember correctly, you had a simple complete demolition (apart from being cautious because of the slope). So there was nothing to gut in the sense of rewinding back to the shell. When clearing out the existing building, it is about very different aspects:

... namely "waste separation," so as not to end up with the total volume in the most expensive landfill category "completely mixed." Then, always balancing cost savings and time investment, as much volume as possible is roughly "pre-sorted" before the sledgehammer is swung. Only copper thieves bother with cables, not demolition contractors.
 

motorradsilke

2024-02-14 23:58:37
  • #6


Why? The gas connection is decommissioned beforehand anyway. After that, you can easily remove them. In our case, they also found a buyer for these together with the radiators.
Here’s a tip: Get in touch with all utility providers as early as possible. Sometimes they take longer than expected. Almost our schedule failed because of disconnecting the gas connection, as they hadn’t indicated on their website that they need 3 months’ notice.

The demolition permit was processed as part of our building application.
 

Similar topics
28.01.2010House with or without a basement? - Experiences20
05.06.2010Basement made of high perforated bricks or concrete?11
18.08.2013Massive house with basement. Is our budget enough?11
11.04.2015Wall as a privacy screen11
17.12.2015Wall on property boundary45
01.02.2017Basement originally partially concrete, now possibly completely brick-built28
26.05.2023How to plaster a wall made of formwork blocks, experiences?13
19.05.2021Evaluation cellar / settlement house Bavaria53
17.04.2024The wall is not level on the base plate or protrudes by 2 cm26
16.03.2020Outdoor facility - Neighbor has already built a wall15
24.07.2020Build a high wall with a door opening12
08.03.2022Cladding/Beautification of wall in the garden30
22.03.2022Plaster or paint a wall made of formwork stones?13
30.03.2021Front yard wall, slope/decline, what to do?12
09.04.2021Mount privacy screen on a sunken, slanted wall12
04.07.2021Is a strip foundation necessary at all for a small wall?23
10.10.2021Demolition cost of an old basement 197011
16.10.2021Demolition/New construction/Renovation/Building on an old basement - ideas & experiences?16
24.03.2023Mounting steel plates on a wall without drilling10
03.08.2023Frost-resistant foundation of a wall next to an existing neighboring fence15

Oben