Completion date in General Contractor Agreement - Wording assistance

  • Erstellt am 2019-05-28 21:26:09

11ant

2019-05-29 00:21:05
  • #1
And what did he do for that, if checking compliance with your wishes was not included? Forget it. If you otherwise ended up with nothing because the funding measure would then expire, that might still be acceptable. But to expect damages from him because you "earned too much" in the next assessment year would probably be going too far. And a guarantee hardly makes sense without a penalty clause. So: tick it off. Plan worst case, i.e. the house smaller by the funding amount (or the bank financing correspondingly higher) - that seems to me unfortunately the most sensible advice.
 

Zaba12

2019-05-29 06:23:57
  • #2
First of all, the development work is still ongoing. That means the plots may not even be surveyed yet. This is taking a while. Just as an example, at the notary appointment (Feb 17) we were promised that the plots would be developed in summer 17. It actually happened in April 18, with surveying and land charge registration then in June 18. There are so many "ifs" involved that you can only let it run.

Or the other way around, my neighbor is now in the 14th month of his construction project. There is definitely no guarantee it will be finished. Not even contractually. What there is, for example, is €10 for each day exceeded starting from the 9th or 12th month, but that doesn't make you happy.
 

Tego12

2019-05-29 06:51:59
  • #3
Offer the site manager half of the [Baukindergeld] if he finishes on time?
 

goalkeeper

2019-05-29 06:58:17
  • #4


The plots have already been surveyed, soil surveys can also already be done, development works finished earlier than planned, building applications already can be submitted, and the building area will be open at the latest from October. Notary appointment in four weeks.

Land charge registration will be done in 4-6 weeks for us, so that the notary didn’t even know what a priority certificate was needed for.

There are also municipalities that work properly and on schedule. I live almost next to the building area and therefore follow the progress and also sometimes speak to the site manager.

I think it’s good when you point out various problems that may arise. However, my question has not been answered so far.
 

goalkeeper

2019-05-29 07:00:15
  • #5


The managing director is also the site manager - he already gets enough
 

Tego12

2019-05-29 07:00:54
  • #6
But she was, probably not in the way you expected (dafür müsstest du zum Anwalt gehen).
 

Similar topics
01.04.2020Construction Manager Area Neukirchen-Vluyn (Duisburg/Kleve/Wesel)10
09.03.2014Construction manager missing10
02.07.2015Question about surveying a property regarding the input plan16
07.06.2016House seller cancels before notary appointment - Schufa38
06.06.2017Local bank markets plots - linked deal26
15.01.2018Can a construction manager resign due to poor performance?16
22.04.2018Construction is continuously delayed - call the site manager?36
31.05.2019The construction manager does not come, does not check, or he doesn't care about anything16
12.08.2019First appointment construction manager - Tips?11
10.11.20202 (dream) properties - financing unclear. Save equity?40
05.08.2021Divide and develop plots themselves24
12.01.2022Union of two plots - redefine the building envelope?20
16.05.2022Which plots are the best in this building area (with plan)?17
05.09.2023Application for a new development area: Selection of plots41

Oben