Building law: Electrician refuses to continue

  • Erstellt am 2020-03-20 09:10:44

nordanney

2020-03-20 11:46:11
  • #1
You were informed about the standard price. You exceed it with your wishes. You could have requested an offer. But in practice, this leads to a house construction taking not 9 months, but 2 years. That is why theory and practice differ greatly in construction. In our last build, we completed many trades on verbal agreement – verbal agreement on prices and verbal acceptance of the offer. The same applies to change requests. Sometimes the craftsman said approximately what it might cost, sometimes there was an invoice later. If the electrician is on site and drills a few additional sockets, I cannot wait for a written offer. Do it or leave it. As I said, this is a learning experience for you. But it has happened exactly as it does daily on thousands of construction sites.
 

dab_dab

2020-03-20 11:47:50
  • #2


Did you necessarily want the pattern specifications and significant changes, or did you just keep ordering merrily as long as no supplementary offer came, in the naive hope that everything would then be included?

If the former, then it's obviously necessary to possibly have the additional services itemized again and then pay for them.
If the latter, it was a bit naive.
 

face26

2020-03-20 11:51:48
  • #3
Asked the other way around. What exactly is your main problem? That it costs more at all, or that it is that much?
 

Alessandro

2020-03-20 11:53:07
  • #4
It was actually the latter. The electrician also explicitly pointed out things to us that are standard nowadays and that we should definitely install sockets for the Christmas lights in the window reveals. He never said anything about the costs and I never even thought of asking about extra costs, as I always assumed high-quality electrical engineering and the developer conveyed the standard service description as the cost estimate, even when the floor plan was not yet final.
 

Alessandro

2020-03-20 11:55:30
  • #5


That I could have consciously decided to pay the extra costs if I had known about it.
Then I wouldn't have 12 sockets in the pantry and 9 in the wardrobe now.
 

face26

2020-03-20 11:55:31
  • #6


And in addition to my question, is the standard construction service description part of the contract?
 

Similar topics
15.01.2014Turnkey construction / self-employed / additional sockets16
24.12.2015Electrical planning - sockets88
15.08.2016Minimum requirements for the number of sockets?11
13.03.2017Construction planning, construction work description, cost breakdown19
12.05.2017Is an advance payment to an electrician lawful?23
12.09.2019Electricity in garage: fuse box, circuit, sockets21
01.12.2017The bank may want a construction service description despite individual subcontract awarding26
31.03.2018Prices have been lumped after modification ideas of the construction service description10
22.06.2018Unauthorized high-quality work - additional costs25
01.08.2018Description of construction services - Performance assessment?12
01.08.2019Trouble with the electrician / tolerance range?!42
12.04.2019Is the construction performance description detailed enough?14
21.07.2021Problem with the electrician - what would you do?78
11.06.2021Construction performance description from the favorite - Is something missing?65
29.03.2022Single-family house KfW55 - Extra costs: rip-off or justified?29
16.08.2022Evaluation of Offer + Construction Description of New Bungalow29
27.12.2022Wiring sockets, switches30
09.07.2023Electrician Cost Estimate - New Installation22
18.03.2025Overview of the offer and construction work description20

Oben