Basis for creditable total construction costs

  • Erstellt am 2024-10-09 07:31:21

mayor333

2024-10-09 18:35:17
  • #1


Of course, it makes no sense to say the architect was recommended to us by very good friends, the mother in turn works for this architect, etc.

Which DIN 276 is that? Building regulations? Thanks

We received the invoice directly with the completed building application, which he submitted without our review. Now three errors have come to my attention, or rather were apparently forgotten by the architect.
P.S. Yes, I could kick myself right now, I also always believe everyone should be paid fairly. But unfortunately, I have the feeling that the ignorance was mercilessly exploited.
 

mayor333

2024-10-09 18:37:45
  • #2


He fully invoiced all 4 phases. Fee zone 3 mid-rate

As a kindness, I was granted a 15% discount at the end.
 

nordanney

2024-10-09 18:49:47
  • #3
Well, if only windows or the front door are replaced, no building permit is required. So there must have been other structural changes somewhere. Maybe walls were actually torn down to turn a small window into a large one... And I would also be interested in that "etc." If I plan the interior of the house luxuriously, you can easily reach half a million (extensive electrical work with home automation, solid oak floorboards at 250€/sqm pure parquet costs, flush-mounted frames/doors up to the ceiling, etc.). Honestly? If you ask me about the costs for the renovation of a 97sqm listed building and thus mean renovation and not just a cosmetic fix-up, I would have named a minimum price of 2,000€/sqm as a basis, but pointed out that a really comprehensive renovation is usually around 2,500€/sqm. Pure experience values. And with that, the architect is not wrong.
 

mayor333

2024-10-09 18:57:45
  • #4


So in our case, the whole process is being carried out under the exemption procedure since there is a development plan that regulates everything.
The architect did not take over any interior planning except for a staircase that is being moved (non-load-bearing) and a door that is being closed off with drywall.

Otherwise, the architect was only responsible for the external changes, but these were only listed and referred to the development plan.

He took a new measurement once for the living space calculation and that was it.

We were not informed about the phases or anything else, the invoice came and that was it. Even now, no cost estimate has been provided to me after repeated inquiries.
 

nordanney

2024-10-09 19:25:40
  • #5

Just Google it. It is the basis for everything related to costs within the framework of the HOAI.

Well, if you are supposed to pay at the end, then ask the architect – referring to the service phases – that a) he has not performed his services and b) has issued an invoice that cannot be verified, since a)

Briefly for you – what is interesting is service phase 2 g) or the cost estimate in service phase 2 or its update in service phase 3





If, of course, he receives a very simple task and does not have to perform most of the possible services, then agreeing on a fee according to HOAI is naturally problematic (for the client), because the architect bases it on the total estimated costs and not simply on a flat fee of X.

Maybe the catalog of his actually necessary tasks (which he did not perform) helps you reach an agreement. He won’t deliver anything more and only accepts a negotiated flat fee.
 

mayor333

2024-10-09 20:14:04
  • #6


A dumb question, why did the architect only indicate costs of €50,000 in the building application itself, but set €240,000 in his HOAI. Typo?
 

Similar topics
28.04.2014Cost estimate - contract for work16
16.09.2014Termination of collaboration with architect - demands excessive fee28
27.12.2015Who has built with an architect? Experiences??85
01.02.2017Building application is becoming increasingly complicated!20
16.05.2017Which security level to choose for windows?29
17.04.2017Civil Engineer vs. Architect17
27.04.2017Carport deviation from the building application21
06.12.2017Constantly making the same mistakes in the building application - stupidity or intent?44
17.12.2018What is set in stone in the building permit application?10
04.01.2022Architect, contract according to HOAI 2013 - refuses to provide service36
08.07.2019Bungalow 135 sqm: Floor plan + windows104
02.12.2020Additional costs / surcharge Higher windows48
05.08.2020Building a garden shed... Is a building permit necessary? Detours?17
10.11.2020The architect is wrong with the estimates. And now?29
15.01.2022Architect unreliable - How to proceed?17
22.01.2022Check cost estimate from preliminary draft35
18.02.2022Floor plan offer from the architect - your opinion11
18.01.2023Architect performance phase 1-4 - Which documents are required?33
27.05.2022Architect - Flat-rate offer instead of HOAI for single-family house12
14.02.2025The planner does not perform any calculations according to DIN 27660

Oben