Are marine exhibitions generally very expensive?

  • Erstellt am 2017-11-15 21:22:56

ruppsn

2017-11-17 12:00:04
  • #1
Hi,

Yes, that happens and that’s just how it is and cannot be changed. Then there is no other way. I don’t think I claimed that there is always and everywhere an option to have materials supplied by the client installed. So I don’t really see where we differ. My point was only that under certain circumstances there are alternatives and good plumbers who would be willing to install client-supplied materials. Possibly Reuter.de’s database could bring up such a tradesman. CAN, not necessarily MUST.

You can certainly do that, but it wouldn’t be my way, because I wouldn’t see much sense in investing in things that I already know I will throw away later.

Or was the motivation to take the standard and replace later rather to avoid endangering the construction schedule (and thus the move-in date), because removing the trade would have caused delays?
I would certainly consider that, because if the delay leads to costs exceeding the standard and subsequent replacement, that would be for me a reasonable and conceivable approach.

If that wasn’t the motivation, I don’t quite understand why standard was installed at all and not just the evening handyman used for the porcelain from the start. Or did the general contractor say it was either everything (i.e., pipe installation, bowls, fittings) or nothing at all (i.e., no pipe installation either)?

In the latter case, I would indeed consider whether the general contractor is the right way for me—depending on how important individuality is to me. We had exactly that back then: the general contractor said, if individuality is desired, then only if the sanitary trades (including pipe installation) and also heating (because the same subcontractor does it) are removed. The “credit” was too low for us, to say the least ridiculous (I think it was 23k for both!). Similar with the electrician and flooring. Ergo we ended up with the architect, because it fits better with our wishes and we have the impression that everything can be better and more finely controlled/influenced. But of course not everyone will see it that way, that’s clear. If you definitely want to build with a general contractor—and there are certainly good reasons for that—the path you described (standard first, then new later) can be an option. It would hurt me as wasted money in that case, but if it pays off for others, why not?

Are we really that far apart? I have the impression we’re not...
 

Nordlys

2017-11-17 12:34:44
  • #2


Exactly. They had sold the old house and had to move out.
 

Roland1983

2019-07-25 08:35:03
  • #3
is intense. was also sent to an exhibition. suddenly the bathrooms cost 40k there. a craftsman who didn’t even do the bathroom for me gave me the tip to better ask at Reuter. Thanks again to Ingo Schäfer, master metalworker from Lindlar. then I found a plumber who did it. bathrooms cost half and were better equipped. crazy whole thing....

you learn for life.
 

Similar topics
10.03.2016New bathrooms - save costs34
22.08.2017Renovation of two bathrooms, what do you think of the current state of the planning?44
15.08.2017Calculation interior finishing: heating, sanitary, bathrooms, floor coverings55
01.10.2020Buy bathroom equipment yourself and settle it with house financing24
05.12.2018Bathroom sampling, saving tips?16
03.10.2021No house, just an apartment: bathrooms tiny11
04.01.2022Two bathrooms: Where should tiles go?49

Oben