The architect owes a plan eligible for approval – whether he needs subcontracted engineers for this is his problem. Let him simply include exactly the shrubs listed in the development plan in the approval plan (he should be able to read it), omit trees where replacement planting is not required, and that’s it. Nobody will come later to tear down the house because geraniums are planted where someone wrote petunias *LOL*
 

sven.conzi

2017-06-12 19:09:52
  • #2
We created a simple sketch with the architect - in color, showing where paving, lawn, hedge, trees, trash bins, and carport are located. That was sufficient for the office.
 

Escroda

2017-06-13 08:41:53
  • #3
The only question is whether the contract is designed so that the costs are included. Otherwise, the architect will have this brokerage service paid for additionally. You can do that. If you read the requirements for the content of such a plan, you will probably estimate the chances of acceptance by the authority as rather low. Get two alternative offers and have the plan created by a professional. When you see the finished plan, you might say, I could have done that too. But figuring out in advance what really matters in the plan is probably difficult. In Bavaria, some things are different. Unless it is a large multi-family house project, I also find the requirement exaggerated but compliant with regulations and therefore unavoidable.
 

V3ctra

2017-06-13 16:07:16
  • #4


That's where the problem lies. But in the construction service description it says: We prepare the complete documents for the building application (scale 1:100) taking into account the local building regulations for submission to the competent authority.

The building application includes:
-the building application form with building description
-the building plans
-the calculation of living space
-the calculation of the enclosed space
-the drainage plans
-the building physics proofs for fire and soundproofing

Unfortunately, there is nothing about open space design plans...
 

11ant

2017-06-13 16:16:15
  • #5
Oh, I see, of course. Not an architect, just a contractor, plan submitter.
 

Jürgenj

2017-06-13 16:24:17
  • #6
Hi,

no explicit plan was required from us, but the architect drew in a few little plants according to our specifications (we already have some ideas), from which it became clear that we are adhering to the [Bebauungsplan].

Costs: none

Regards Jürgen
 

Similar topics
19.07.2018Draw the plan yourself? Do you necessarily need an architect?11
18.02.2011Architect totally messed up - experiences?17
30.09.2012Final invoice architect13
27.10.2013Architect --> Agreements? What is that?21
16.04.2014Cost of soil survey - Does the architect pay or do we?12
16.09.2014Termination of collaboration with architect - demands excessive fee28
01.10.2014Collaboration with an architect - how does it work properly?22
25.02.2015Planning / Architect, involvement of specialist planners for the approval plan10
10.04.2015Cost estimate architect single-family house. Your assessment44
15.06.2015Garage - Building Application - Confusion36
27.12.2015Who has built with an architect? Experiences??85
01.02.2017Building application is becoming increasingly complicated!20
27.04.2017Carport deviation from the building application21
06.12.2017Constantly making the same mistakes in the building application - stupidity or intent?43
15.12.2017Expected construction costs in Hessen: architect vs contractor93
11.05.2018Construction application costs only 40 euros due to exemption application?27
07.09.2021Floor plan tube house L-shape triangular plot including oak tree529
05.08.2020Building a garden shed... Is a building permit necessary? Detours?17
09.05.2022Building application due to parking spaces not approved. What can happen?30
18.02.2022Floor plan offer from the architect - your opinion11

Oben