Building application due to parking spaces not approved. What can happen?

  • Erstellt am 2021-11-30 21:09:00

NDDTs01

2022-03-16 13:26:16
  • #1


Yes, that's how we see it as well.

The last time we submitted, it was not confirmed, but we have a return receipt for it. And if they had not received it, they should have sent a rejection by now.
 

gutentag

2022-03-16 19:52:11
  • #2
What is a 3-month deadline? I only know it as a guideline.
 

NDDTs01

2022-03-17 09:41:05
  • #3


Hessian Building Code (HBO) §65 paragraph 2: 1 The receipt of the complete building application must be confirmed, including the date. 2 A decision on the building application must be made within three months of receipt of the complete application; the building supervisory authority may extend this period by up to two months for good cause. 3 The building permit is deemed granted if no decision has been made on the building application within the deadline specified in sentence 2.
 

11ant

2022-03-17 13:43:14
  • #4
If I understood correctly, the authority did indeed fail to deliver such a confirmation letter ... ... however, the decisive factor for the start of the period here is clearly the completeness as such, independent of the issuance or date of a receipt confirmation. And sentence 2 would have given the authority the option to confirm the receipt with the addition of the notification that it (indicating the "important reason") would need the extension of the period – e.g. exceptional sick leave, or many employees seconded to the health department for Corona contact tracing. If the authority has not asserted any such reason, I see the three-month period as remaining valid (and its expiry without further ado triggering the consequence of the permit fiction).
 

NDDTs01

2022-03-29 09:14:20
  • #5
We have finally reached someone from the building authority and the lady confirmed that our project has gone into fiction. She will confirm this in writing by Thursday. Now we just have to hope that the KFW launches programs again. Unfortunately, our bank did not submit the KFW application on time.
 

NDDTs01

2022-05-09 14:32:20
  • #6
Update: The building authority in Karben has withdrawn its opinion on the fiction. Although they had not responded for almost 4 months and had deliberately let all projects run under fiction because they lacked manpower, one of our parking spaces is 50cm too close to the property boundary, so our application is incomplete and not under fiction.

We are currently checking whether legal action is possible.
 

Similar topics
07.04.2016New KfW conditions from 04/201674
30.03.20162016 KfW Efficiency House 55 according to reference values (U-values)39
30.10.2015Can the building application be submitted this year?14
22.12.2015KFW 70 funding still in 201524
16.01.2016KfW-70 standard not reached (bungalow)21
29.01.2016Price difference new construction, KfW 70, KfW 5513
17.02.2016KFW 55 in semi-heated basement - cold basement31
10.05.2016KfW funding for two-family house26
11.05.2018Construction application costs only 40 euros due to exemption application?27
26.02.2019Submit a building application before the land is paid for?11
30.11.2020Building Authority Problems - Purchased a Defective Plot56
05.08.2020Building a garden shed... Is a building permit necessary? Detours?17
30.01.2021The building authority rejects the building application because the house is planned too far back86
18.11.2021KfW funding for KfW 40 Plus houses from now and from 01.07.202157
17.04.2021New KfW Building Loan Conditions17
08.10.2021Building application: What happens next?16
14.06.2022KfW BEG funding stopped 261, 262, 263, 264, 461, 463, 4641239
03.03.2023Building permit application without height survey?15
10.03.2023Preliminary building approval positive, building application criticized position29
24.11.2024Building authority requires open space design plan for single-family house - experiences?37

Oben